Electrical Design
This section provides electrical design guidelines for Power Block 2000.
Electrical Supply Requirements
This section provides electrical supply guidelines for Power Block 2000.
Electrical Input
Power Block 2000 requires the following electrical service characteristics:
-
Supply system: 230/400 V AC, 3-phase grounded WYE (Y) configuration
-
Frequency: 50 Hz
-
Maximum input current: 850 A
-
Required conductors: L1, L2, L3, and Protective Earth (PE)
-
Neutral conductor: Not required for standard charging applications
-
400 V AC 3-phase Delta (D) configuration (including corner-grounded Delta transformer) is not acceptable.
-
Express Solo is available in two factory configurations: with neutral landing or without neutral landing. A Neutral connection is not required for standard charging applications. Certain Vehicle-to-Grid (V2G) applications may require phase-to-neutral voltage measurements for control functions. Contact ChargePoint before planning a V2G deployment to ensure the correct Express Solo configuration is selected.
Branch Circuits and Overcurrent Protection
EV
Electric Vehicle charging equipment operates as a continuous load, drawing high current for extended periods. Branch-circuit conductors and protective devices must therefore be sized in accordance with applicable local electrical regulations for continuous‑load operation.
When planning multiple EV
Electric Vehicle charging stations, it is best practice to segment non-continuous and continuous loads, with all branch circuits for EV
Electric Vehicle charging on a dedicated electrical panel assembly with adequate circuit breakers. When sizing new electrical panels dedicated for EV
Electric Vehicle charging, all branch circuits must support continuous load.
Power Block 2000 is available in multiple power ratings: 350 kW, 500 kW, 525 kW
Each Power Block 2000 requires its own circuit breaker. Recommended breaker sizing is given below. Check with local code for breaker size requirements.
Recommended breaker size for the Europe region (400 V AC):
|
Max. Output Power |
Continuous Input Current |
Recommended breaker size |
|---|---|---|
|
350 kW |
542 A |
600 A |
|
500 kW |
789 A |
800 A |
|
525 kW |
800 A |
900 A |
Power Block 2000 has a short circuit current rating of 100 kA.
Power Block 2000 is tested to IEC 61000-4-5, Level 5 (6 kV @ 3000 A) standards.
Grounding and Earthing Requirements
Power Block 2000 is categorized as class 1 equipment and therefore its chassis must be connected to a grounded, conductive, and permanent wiring system in accordance with IEC 60364 and/or applicable national standards.
Power Block 2000 provides an isolated DC output. The DC positive and negative conductors must not be bonded to ground or protective earth. Grounding requirements apply to the equipment chassis only.
Provide a PE conductor sized according to local regulations.
Earthing systems
TN-S
Terra Neutral Separate, TN-C
Terra Neutral Combined-S, TN-C
Terra Neutral Combined, and TT type supply networks are supported, subject to local codes. Connect Power Block 2000 only to the following systems:
-
TN-S
Terra Neutral Separate 230/400 V AC, 3-phase, grounded WYE -
TN-C
Terra Neutral Combined-S 230/400 V AC, 3-phase, grounded WYE -
TN-C
Terra Neutral Combined 230/400 V AC, 3-phase, grounded WYE -
TT 230/400 V AC, 3-phase, grounded WYE
If connecting Power Block 2000 to a TT network, refer to Residual-current devices (RCDs) for further requirements.
Do not connect Power Block 2000 to IT 400 V AC systems.
Residual-current devices (RCDs)
If an RCD
Residual Current Device has to be installed in the supply line per code (as is usual for installation in the TT network), contact ChargePoint for RCD
Residual Current Device selection.
Grounding and bonding sequence
When connecting Power Block 2000 to Power Links, charging components must be ground bonded in sequence from Power Block 2000 to Power Link.
Disconnect and Emergency Shutoff
Power Block 2000 ships with an AC disconnect switch for emergency shutoff. The switch is located on the intake side of the Power Block 2000 cabinet.
Shunt Trip Wiring (optional)
Each cabinet of Power Block 2000 provides a set of unpowered (dry) contacts to connect to an optional shunt trip device. These contacts are rated to 240 VAC and 6 amps.
Wiring sections to and from Power Block 2000 are deactivated when unsafe conditions are detected, such as unintended cover panel removal. A breaker reset is required any time the shunt trip is activated.
If installed, each cabinet of the Power Block 2000 must be wired to the shunt trip unit of its own upstream circuit breaker. Upstream AC power must be shut off at the panel to remove shock risk inside the Power Block 2000. All shunt trip behavior is already hard-coded into the Power Block 2000 and has no programmable variables.
Emergency stop devices are governed by local and regional codes and may be required in some sites. If one is required by code or by the site, confirm specifications with your ChargePoint representative.
-
Electrical panel
-
Power Block 2000
-
Control voltage supply, maximum 240 VAC
-
Shunt trip circuit breaker
-
Shunt trip coil
-
Auxiliary contacts (closed when main contacts are closed)
-
3-phase AC main
-
Power Block 2000 shunt trip contacts, Normally Open (inside the auxiliary power supply, accessible on field wiring terminal block)
-
3-phase Power Block 2000 AC input
Soft Shutdown
The soft shutdown function is an optional feature that can be installed as a way to stop a charge session on a Power Block 2000. It is not meant to safely service the Power Block 2000 or take the place of a AC disconnect switch.
Each cabinet of a Power Block 2000 supports connection to a soft shutdown switch.
To use this feature, the installer must select and mount a physical soft shutdown switch (one per Power Block 2000 cabinet) with the following specifications:
-
Building wire rated to 600 V and suitable for the installation environment (e.g., dry, damp, or wet locations)
-
Normally Open (NO) configuration
-
Switch current of 2 mA
-
Switch voltage of 48 V
-
Gold contacts suggested
When creating the site drawings, consider where any soft shutdown switches should be positioned. If applicable, consider disability and accessibility regulations for your region when choosing switch locations.
Soft shutdown switch requires a dedicated wire conduit. For more information, refer to Conduit Requirements.
When the switch is closed, the Power Block 2000 software ends the current charging session with a normal stop, then opens DC contactors in the Power Block 2000 cabinet. The station stays in this state regardless of station power, not allowing operation. Only a service technician can place the Power Block 2000 cabinet back into service after the switch is reset to Open.
WARNING: The external DC output wires from the Power Block 2000 could still be energized with the switch closed.
Safety Hub
Safety Hub is a Power Block 2000 feature that provides continuous electrical-isolation monitoring to enhance system safety. When required, Safety Hub uses a dedicated twisted-pair connection routed from the Power Block 2000 Safety Hub Board to each associated Power Link. These conductors may share the same conduit as the 48 V DC and Ethernet wires serving the Power Links.
Safety Hub wiring requirements vary by Power Link model. Depending on the specific Power Link used in the installation, one of the following configurations will apply:
-
Some Power Link models require a direct Safety Hub twisted-pair connection between the Power Block 2000 Safety Hub Board and the Power Link.
-
Other Power Link models do not require a Safety Hub wire connection. For these models, a jumper wire must be installed on the Power Block 2000 Safety Hub Board instead of running twisted-pair wiring to the Power Link. This jumper is supplied with the Power Link and does not need to be sourced separately. Installation details are provided in the Express Distro Power Block 2000 Installation Guide.
Refer to the site design guide and installation guide of the Power Link model specific to your project to determine whether Safety Hub twisted wire connection is required.
Wiring and Conduit Requirements
Refer to the Express Distro Power Block 2000 Datasheet at ChargePoint Product Reference Documentation for full product specifications. Using that data, ensure that the installation location is equipped with service wiring that support the station's power requirements.
Conduit and wire size are determined based on current. Service wiring in conduit or armored cable must be run as required to comply with local electrical codes. Consult national and local codes or a project engineer to determine the grade, quality, and size of the conduit or cable.
-
All wiring and conduit is supplied by the contractor unless otherwise indicated.
-
For V2G and energy storage applications, contact ChargePoint for wire and conduit requirements.
Wire Run Lengths
Wire run length guidelines are given below:
-
The maximum total external DC output wire run length from a Power Block 2000 to a connected EVSE
Electric Vehicle Supply Equipment (such as a Power Link 2000) must not exceed 200 m (656 ft). Refer to the cluster configuration provided by ChargePoint for interconnect details. -
48 V DC wire and Ethernet run length between Power Block 2000 and a Power Link must not exceed 200 m (656 ft).
-
At minimum, there must be one 48 V DC wire pair connecting from the Power Block 2000 to each Power Link. If the distance between the Power Block 2000 and a Power Link exceeds 100 m (328 ft), contact ChargePoint to determine if an additional 48 V DC wire pair must be run to compensate for voltage drop.
Ethernet Cable Type and Configuration
Specifications for Ethernet cable type and configuration are given below:
-
For Ethernet communications between any two nodes (for example, between a Power Block 2000 and a Power Link):
-
For distances up to 100 m (328 ft): use outdoor-rated Cat6 Shielded Twisted Pair (STP
Shielded Twisted Pair) cable. Lesser grades of cable do not provide the required noise immunity. -
For distances between 100 m (328 ft) and 200 m (656 ft): use an extended-reach cable rated for 200 m (328 ft).
-
-
An Ethernet cable run between a Power Block 2000 and a Power Link must have the shield terminated only at the Power Block 2000 end, not at the Power Link end.
Conduit Requirements
In regions that use conduits, wire conduits may enter Power Block 2000 through a Concrete Mount Template (CMT) or through a skid via conduit stub-ups. In regions that do not use conduits and/or use armored cables, the cables may be laid per the conduit layout defined by the CMT.
If using conduits:
-
Conduits must be sealed to maintain a Pollution Degree 2 environment.
-
Conduits must not have bell ends. Conduits with bell ends may interfere with tolerances inside the Power Block 2000.
-
If using conduit stub-ups (ie., not using surface conduit entry), conduits must stub-up 13–25 mm (0.5–1 in) above the mounting surface.
Below is a sample depiction of wire entry via conduit stub-ups.
|
Ref |
4 DC Output |
8 DC Output |
|---|---|---|
| (1) |
Cabinet front side |
|
| (2) |
Cabinet intake (right) side |
|
| (3) |
48 V DC, Ethernet, and Safety Hub |
|
| (4) |
AC input |
|
| (5) |
Shunt trip |
|
| (6) |
EXT A |
EXT A |
| (7) |
EXT B |
|
| (8) |
EXT B |
EXT C |
| (9) |
EXT D |
|
| (10) |
EXT C |
EXT E |
| (11) |
EXT F |
|
| (12) |
EXT D |
EXT G |
| (13) |
EXT H |
|
IMPORTANT: The following table provides the maximum size and quantity of conduits that can be installed on Power Block 2000 configured for standard wire entry. The actual conduit size and quantity must be chosen based on site specific wiring requirements.
|
Conduits For |
Conduit Quantity x Size (O.D.) |
|---|---|
|
AC input |
3 x 103 mm max. or 4 x 78 mm max. |
|
Exernal DC output (E.g. EXT A, EXT B, EXT C, EXT D) |
1 x 103 mm max. per output or 2 x 78 mm max. per output |
|
48 V DC, Ethernet, and Safety Hub (*) |
1 x 27 mm to each Power Link 1 inch size conduit is required. The quantity of conduits will depend on the configuration. |
|
Optional Features (Soft shutdown switch and shunt trip) |
1 x 21 mm max. per feature |
(*) 48 V DC, Ethernet, and Safety Hub wires travel in the same conduit when connecting Power Block 2000 to a Power Link. Safety Hub wires are required for only for certain models of Power Link. Refer to the site design guide and installation guide of the Power Link model specific to your project to determine whether Safety Hub twisted wire connection is required.
Wire Terminal and Bus Bar Locations
This section illustrates terminal and bus bar locations for the Power Block 2000 in a 4 DC output configuration. Illustrations for 8 DC output and 12 DC output configurations will be provided in a future revision.
The following identifies the wire ports, terminals, and bus bars accessible from the intake side (right side) of each Power Block 2000 cabinet. (Safety shields are hidden from view.)
|
Ref |
Part |
|---|---|
| (1) |
Safety Hub ports |
| (2) |
Ethernet ports |
| (3) |
Terminal block for 48 V DC and soft shutdown switch wires |
| (4) |
Shunt trip terminals |
| (5) |
EXT A bus bars |
| (6) |
EXT B bus bars |
The following identifies the wire ports, terminals, and bus bars accessible from the exhaust side (left side) of each Power Block 2000 cabinet (Safety shields are hidden from view).

|
Ref |
Part |
|---|---|
| (1) |
Ground/PE bar (with wire landing studs) |
| (2) |
EXT D bus bars |
| (3) |
EXT C bus bars |
| (4) |
AC input (L1, L2, L3) and neutral bus bars |
AC input and external DC output conductors must extend a minimum height of 600 mm (24 in) from the finished mounting surface to ensure they reach their landings.
Wire Specifications
The requirements and specifications in this section reflect what is supported by Power Block 2000. When Power Block 2000 is connected to another ChargePoint product, such as a Power Link charging dispenser or battery, conductor characteristics may be further constrained by the connected product. Refer to the site design guide for each connected product and follow the most stringent requirements.
The following table summarizes the conductor requirements for each circuit.
|
Circuit / Application |
Min. Conductor Voltage Rating |
Number of Poles |
Insulation Type |
Conductor Material / Min. Temperature Rating |
|---|---|---|---|---|
|
AC Input |
0.6/1 kV, or as required by applicable national and local electrical installation codes |
3 + PE
|
Select type to be suitable for the installation environment (e.g., dry, damp or wet conditions) |
Must be copper or aluminum, rated for 90°C (194°F)
|
|
External DC Output |
1000 V |
2 + PE |
Select type to be suitable for the installation environment (e.g., dry, damp or wet conditions) |
Must be copper or aluminum, rated for 90°C (194°F) |
|
48 V DC Output |
300 V |
2 |
Select type to be suitable for the installation environment (e.g., dry, damp or wet conditions)
|
Copper wire only
|
|
Shunt Trip |
Same voltage rating as AC input conductors (due to routing proximity to power conductors) |
Twisted pair |
||
|
Safety Hub |
300 V |
Twisted pair |
IMPORTANT: Following are wire design specifications for Power Block 2000, including the maximum quantity and size that the wire terminals can accommodate. All sizing assumes a maximum ambient temperature of 50 °C (122 °F). Where the maximum wire size is listed, the actual wire quantity and size must be chosen based on site-specific wiring requirements and in accordance with the maximum allowed conduit filling rate per local code.
|
Wire |
Max. Current |
Quantity |
Size |
|---|---|---|---|
|
AC input |
350 kW unit: 542 A 500 kW unit: 789 A 525 kW unit: 800 A |
Max. 18 wires (six per phase) |
Max. 150 mm2 (1-core unarmored). Alternates allowed if bend radius ≥ 200 mm (7.9 in) and lug width ≤ 36 mm (1.3 in) |
|
AC protective earth (PE) |
- |
Max. 3 wires (1 per AC conduit) |
Refer to local code for size |
|
External DC outputs (E.g. EXT A, EXT B, EXT C, EXT D) |
250-600 A, depending on Power Link model and configuration |
Max. 8 wires per output (four per pole) |
Max. 150 mm2 (1-core unarmored). Alternates allowed if bend radius ≥ 200 mm (7.9 in) and lug width ≤ 36 mm (1.3 in) |
|
DC grounding |
- |
Max. 2 wires per DC output (1 per output conduit) |
Refer to local code for size |
|
48 V DC output |
32 A |
Max 4 wires per connected Power Link (2 wire pairs; each pair has one wire per pole) (*) |
16 mm2 |
|
Ethernet |
- |
1 per connected Power Link 1 for hardwire Ethernet (if needed) |
Outdoor-rated Cat6 STP |
|
Safety Hub |
- |
2 wires per connected Power Link (***) |
2.5 mm2 |
|
Soft shutdown switch |
- |
2 wires |
2.5 mm2 |
|
Shunt trip |
6 A |
2 wires |
2.5 mm2 |
(*) The required number of 48 V DC wire pairs depends on the distance between Power Block 2000 and Power Link. See Wire Run Lengths. (**) The required Ethernet cable type depends upon the cable run length. See Ethernet Requirements. (***)Safety Hub is required only for certain models of Power Link. Refer to the installation guide of the Power Link model specific to your project to determine if Safety Hub twisted wire connection is required.
For AC input, Power Block 2000 allows a maximum of 18 total current carrying conductors. If utilizing this wiring configuration, install spreader bars at the breaker or transformer to split the outputs across the high number of conductors.
After pulling conductors through conduit, all AC input and external DC output conductors must undergo insulation resistance testing to verify that insulation has not been damaged during the pull.
Plan for lugs and terminations using the following information:
-
Use copper lugs for copper conductors and aluminum lugs for aluminum conductors. The lugs must be nickel-, tin-, or silver-plated compression lugs (not mechanical lugs). Nickel-plated lugs installed with dielectric grease are recommended.
-
When using aluminum lugs, ChargePoint recommends applying an appropriate antioxidant compound to aluminum conductors when terminating into tin-, nickel-, or silver-plated lugs, where required by code or specified by the lug manufacturer.
|
Wire |
Termination |
|---|---|
|
AC input |
Lug: Compression lug; short barrel and tongue with single hole sized for M12 (0.5 in) stud Max. tongue width: 36 mm (1.3 in). |
|
AC PE/ground |
Lug: Short barrel and tongue with single hole sized for M6 (0.25 in) stud |
|
External DC output |
Lug: Compression lug; short barrel and tongue with single hole sized for M12 (0.5 in) stud. Max. tongue width: 36 mm (1.3 in). |
|
DC grounding |
Lug: Short barrel and tongue with single hole sized for M6 (0.25 in) stud. |
|
48 V DC output |
Stripped wire end or ferrule |
|
Ethernet |
RJ45 connector, shielded |
|
Safety Hub |
Stripped wire end |
|
Soft shutdown switch |
Stripped wire end or ferrule |
|
Shunt trip |
Stripped wire end or ferrule |