Electrical Design

This section provides electrical site design specifications for the Power Block and Power Link 2000.

Conduit and wire size are determined based on current. Service wiring in conduit or armored cable must be run as required to comply with local electrical codes. Consult national and local codes or a project engineer to determine the grade, quality, and size of the conduit or cable.

The Power Block is available in 200, 250, 350, and 500 A versions, each with its own rating labels.

All wiring and conduit is supplied by the contractor unless otherwise indicated.

If a site requires surface conduit entry installation, contact ChargePoint before beginning work to obtain an approved installation method. If the station is being fed power by more than two Power Blocks, surface conduit entry installation is not permitted.

The following illustration shows sample electrical circuit requirements along with optional components for Express Plus with single Power Block and Power Link 2000.

sample electrical circuit requirements

  1. Transformer configuration

  2. Ground connection

  3. Electrical panel

  4. Circuit breakers

  5. AC disconnect switch (optional)

Power Block Electrical Supply Requirements

Power Block electrical supply requirements are given below.

Transformer Configuration

Refer to the following table for the transformer configuration.

Transformer Configuration
  North America Europe

Input rating

480 V AC, 3-phase, 260 A, 60 Hz

400 V AC, 3-phase, 310 A, 50 Hz

Electrical service configuration

277/480 V AC 3-phase grounded WYE (Y) configuration

230/400 V AC, 3-phase grounded WYE (Y) configuration

Product connection

Power Block must be connected to L1, L2, and L3 (neutral not required)

Delta (floating or grounded) is not supported.

Neutral is not required for system operation, however Neutral-to-ground bonding is required at the Main Distribution Panel (MDP) supplying the charging station.

This requirement is applicable to installations carried out within the province of Québec, Canada. Whether using a step-up or step-down autotransformer, refer to the 'Hydro-Québec bulletin - Choosing the right one 600/480 V transformer', that is publicly available, for specific guidance.

AC Breaker Size

Charging stations are considered continuous load devices (EVs draw maximum load for long durations). Therefore, electrical branch circuits to EVClosed Electric Vehicle chargers must be sized at 125% of the load on each leg of a 3‑phase panel for North American installations, in accordance with National Electric Code requirements. For other regions, refer to local code.

When planning multiple EVClosed Electric Vehicle charging stations, it is best practice to segment non-continuous and continuous loads, with all branch circuits for EVClosed Electric Vehicle charging on a dedicated electrical panel assembly with adequate circuit breakers. When sizing new electrical panels dedicated for EVClosed Electric Vehicle charging, all branch circuits must support continuous load.

Each Power Block requires its own circuit breaker as follows:

AC Circuit Breaker Size

Region

Nominal Voltage

Max. AC Input Current

Continuous Load (125%)

Breaker Size

Europe

400 V

315 A

394 A

400 A

North America

480 V

260 A

325 A

350 A and 400 A

The Power Block has a short circuit current rating of 65 kA.

AC Disconnect Switch (optional)

A local AC disconnect switch, separate from the shunt trip wiring, is recommended to be installed between each Power Block and the electrical panel. This is especially important if the main electrical panel or utility room is distant, out of line of sight, or has restricted access. For North America installations, refer to disconnect switch requirements per NECClosed National Electric Code Article 625, “Electric Vehicle Charging and Supply Equipment Systems”. For other regions, refer to local code.

Shunt Trip Wiring (optional)

The Power Block provides a set of unpowered (dry) contacts to connect to an optional shunt trip device. These contacts are rated to 240 V AC and 6 Amps.

Wiring sections to and from the Power Block are deactivated when unsafe conditions are detected, such as unintended cover panel removal. A breaker reset is required any time the shunt trip is activated.

If installed, each Power Block must be wired to the shunt trip unit of its own upstream circuit breaker. Upstream AC power must be shut off at the panel to remove shock risk inside the Power Block. All shunt trip behavior is already hard-coded into the Power Block and has no programmable variables.

Emergency stop devices are governed by local and regional codes and may be required in some sites. If one is required by code or by the site, confirm specifications with your ChargePoint representative.

Shunt Trip Wiring Diagram

  1. Electrical panel

  2. Power Block

  3. Control voltage supply, maximum 240 V AC

  4. Shunt trip circuit breaker

  5. Shunt trip coil

  6. Auxiliary contacts (closed when main contacts are closed)

  7. 3-phase AC main

  8. Power Block shunt trip contacts, Normally Open (inside the auxiliary power supply, accessible on field wiring terminal block)

  9. 3-phase Power Block AC input

Grounding Requirements

Express Plus is a metallic accessible enclosure and relies on protective earth or ground connection for protection against electrical shock.

Express Plus must be connected to a grounded, metal, permanent wiring system. An equipment-grounding conductor must be run with circuit conductors and connected to an equipment-grounding terminal on the Power Block.

A grounding conductor that complies with applicable codes must be grounded to earth at the service equipment or, when supplied by a separate system, at the supply transformer, or may be grounded to an earth electrode. Ensure the grounding conductor complies with all applicable codes.

  • North America: A service ground conductor must be run with circuit conductors and connected to an equipment-grounding terminal on the Power Block.

  • Europe: Use TN-SClosed Terra Neutral Separate, TN-CClosed Terra Neutral Combined-S, or TT configurations. Express Plus doesn't have Residual Current Device (RCDClosed Residual Current Device) protection on the AC input side. When RCDs are to be installed, they should be minimum Type A and have leakage current tripping of at least 300 mA. This is because leakage current from Power Block can reach up to 200 mA at full power. The RCDClosed Residual Current Device must detect and disconnect all power lines.

All Express Plus components (Power Block and Power Link 2000) must be bonded to one another in sequence.

Power Link 2000 Site Considerations

This section provides electrical site design considerations specific to the Power Link 2000.

Power Link 2000 Soft Shutdown

The soft shutdown function is an optional feature that can be installed as a way to stop a charge session on that Power Link 2000. It is not meant to safely service the Power Link 2000 or take the place of a HVClosed High Voltage disconnect switch.

To use this feature, the installer must select and mount a physical soft shutdown switch (one per Power Link 2000) with the following specifications:

When creating the site drawings, consider where any soft shutdown switches should be positioned. If applicable, consider disability and accessibility regulations for your region when choosing switch locations.

Soft shutdown switch requires a dedicated conduit. For more information, refer to Civil and Mechanical Design.

To wire the soft shutdown switch to the Power Link 2000:

  1. Run the wiring in a dedicated LVClosed Low Voltage conduit into the Power Link 2000.

  2. Route the wire away from other conductors carrying large currents.

  3. Twist the two wires together, using a minimum of five twists per foot.

  4. Connect the two terminals of the switch to the terminal block inside the Power Link 2000 labeled “Soft_Shutdown”, next to the 48 VDC terminals (described in the Express Plus Power Link 2000 Installation Guide). The terminals do not have fixed polarity.

When the switch is closed, the Power Link 2000 software ends the current charging session with a normal stop, then opens DC contactors in the Power Link 2000. The station stays in this state regardless of station power, not allowing operation. Only a service technician can place the Power Link 2000 back into service after the switch is reset to Open.

The HV DCClosed High Voltage Direct Current wires from the Power Block could still be energized with the switch closed.

DC Maintenance Switch (optional)

A maintenance switch is highly recommended when more than one Power Link 2000s are connected to one or multiple Power Blocks to improve system uptime during maintenance. For Power Link 2000s that do not have a maintenance switch, servicing the station requires the Power Block(s) upstream to be powered off. This can affect system uptime and fleet scheduling.

If an external DC disconnect switch is used, then the switch must be configured with Normally Closed (NC) contact feedback wired into each Power Link 2000. The DC Maintenance Switch is an optional part available for the pedestal-mount Power Link 2000. It is ordered and shipped separately and is field installed.

Sequential Charging Kit

Dual output Power Link 2000s may be configured for sequential charging by field installing a Sequential Charging Kit. This kit allows Power Link 2000 to take a single power input and feed the power to either output in a sequential manner. The Sequential Charging Kit is ordered separately and is field installed.

Ethernet-to-USB (ETH2USB) Kit

Ethernet to USBClosed Universal Serial Bus is an optional kit that allows an Express Plus cluster (interconnected Power Blocks and Power Link 2000s) to have a hardwired Ethernet connection with an external network server.

The Ethernet to USBClosed Universal Serial Bus kit is installed within a single Power Link 2000, providing network connection for every node in the Express Plus cluster. The installation requires a conduit for the Ethernet cable, which must be run from the customer server or network equipment directly to the Power Link 2000.

This kit must be ordered separately and installed in the field.

Wiring Requirements

For full product specifications, refer to the Express Plus Datasheet. Using that data, ensure the installation location is equipped with service wiring that supports the Express Plus site’s power requirements:

All AC and DC high voltage wires must undergo insulation testing as outlined in the Express Plus High Voltage Wire Insulation Resistance Test Field Guide.

Notes For All Regions:

Wire run lengths

  • The maximum total HV DCClosed High Voltage Direct Current wire run length from any Power Block to any connected Power Link 2000 must not exceed 200 m (656 ft). Refer to the cluster configuration provided by ChargePoint for interconnect details.

  • LV DCClosed Low Voltage Direct Current wire and Ethernet runs between nodes (Power Block and Power Link 2000):

    • For non-LCCClosed Liquid Cooled Cable cables:

      • Without daisy-chained 48 V, the 48 V and Ethernet wire run length between Power Block and Power Link 2000 can be up to 200 m (656 ft).

      • With Power Link 2000 connected in a chain, the maximum total wire run length from the Power Block to the furthest Power Link 2000 is 160 m (525 ft). Contact ChargePoint for options if greater lengths are needed.

    • For LCCClosed Liquid Cooled Cable cables:

      • The 48 V and Ethernet wire run length between Power Block and Power Link 2000 can be up to 100 m (328 ft). Contact ChargePoint for options if greater lengths are needed.

  • The maximum wire run length between a Power Link 2000 and an external network connection is 200 m (656 ft). Refer to the cluster configuration provided by ChargePoint for interconnect details.

Ethernet requirements

  • For Ethernet communications between any two nodes (Power Link 2000 or Power Block) or to an external network connection:

    • Distances up to 100 m (328 ft) must use outdoor-rated Cat6 Shielded Twisted Pair (STPClosed Shielded Twisted Pair) cable. Lesser grades of cable do not provide the required noise immunity.

    • Distances between 100 m (328 ft) and 200 m (656 ft) must use Paige OSP Shielded GameChanger cable. See paigedatacom.com/gamechanger.

  • An Ethernet cable connecting a Power Block and a Power Link 2000 must have the shield terminated at the Power Block end.

  • An Ethernet cable connecting two Power Link 2000s must have the shield terminated at the end nearer to the Power Block.

  • An Ethernet cable connecting a Power Block to another Power Block must have the shield terminated at only one end; either end can be terminated.

Conduit requirements

Other requirements

  • Use one AC input feed per Power Block.

  • Make sure to consider the height of bus bars above the concrete pad when determining the wire length required.

    Power Block

    Power Link 2000

    Power Block bus bar height

    Power Link 2000 bus bar height

The following sections provide the maximum wire sizes that can be landed onto the Power Block and Power Link 2000 bus bars. All sizing assumes a maximum ambient temperature of 50 °C (122 °F).

Power Block

Power Block takes AC input from the site and provides DC and Ethernet output to Power Link 2000(s).

Wire Entry and Landing

Power Block Wire Entry and Landing

  1. AC input

  2. Ground input

  3. HV DCClosed High Voltage Direct Current output

  4. Ground output

  5. LV DCClosed Low Voltage Direct Current output

  6. Ethernet output

Following are wire specifications for the Power Block, including the maximum quantity and size that the wire terminals can accommodate. All sizing assumes a maximum ambient temperature of 50 °C (122 °F). Where the maximum wire size is listed, the actual wire quantity and size must be chosen based on site-specific wiring requirements and in accordance with the maximum allowed conduit filling rate per local code.

AC Input Wire Quantity, Size, and Termination

AC Input Wire Specifications
Wire Quantity Size Termination

AC input

Max. 12 wires

(four per pole)

Max. 400 mm2

(750 MCM)

Lug: Long barrel and tongue with two holes spaced 44.5 mm (1-3/4 in) apart and sized for M12 studs

Max. tongue width: 47.5 mm (1-7/8 in)

Ground

1 wire

Refer to the local code for size

Lug: Short barrel and tongue with single hole sized for M12 stud

DC Output Wire Quantity, Size, and Termination

DC Output Wire Specifications
Wire Quantity Size Termination

HV DCClosed High Voltage Direct Current outputs

A and B

Max. 12 wires

(six per output, three per pole)

See Power Link 2000 Wire Quantity, Size, and Termination

Lug: Long barrel and tongue with two holes 44.5 mm (1-3/4 in) apart and must fit M12 stud. Max. tongue width is 49 mm (1-15/16 in)

Ground

Max. 4 wires (one per Power Link 2000)

See Power Link 2000 Wire Quantity, Size, and Termination

Lug: Short barrel and tongue with single hole and must fit M12 stud

LV DCClosed Low Voltage Direct Current output

See Power Link 2000 Wire Quantity, Size, and Termination

Stripped wire end

Ethernet

See Power Link 2000 Wire Quantity, Size, and Termination

RJ45 connector, shielded

Power Link 2000

The Power Block DC (HVClosed High Voltage and LVClosed Low Voltage) and Ethernet outputs are the inputs for the Power Link 2000. The Power Link 2000 provides HV DCClosed High Voltage Direct Current output to pantograph(s) and provides LV DCClosed Low Voltage Direct Current and Ethernet output to PD Controller(s). In some Express Plus architectures, Power Link 2000 also provides DC (HVClosed High Voltage and LVClosed Low Voltage) and/or Ethernet output to another Power Link 2000.

Wire Entry and Landing - Pedestal-Mount Power Link 2000

Depending on configuration, the pedestal-mount Power Link 2000 has one or two HV DCClosed High Voltage Direct Current power paths, named A and B. Each power path has two wire landings, an upper landing and a lower landing. Power Link 2000s with a single charging cable are configured with Power Path B landings only.

Pedestal-mount Power Link 2000 wire entry and landing

(a1) HV DCClosed High Voltage Direct Current Power Path A, upper landing

(a2) HV DCClosed High Voltage Direct Current Power Path A, lower landing

(b1) HV DCClosed High Voltage Direct Current Power Path B, upper landing

(b2) HV DCClosed High Voltage Direct Current Power Path B, lower landing

(c) Ground

(d) LV DCClosed Low Voltage Direct Current

(e) Ethernet

Wire Entry and Landing - Wall and Overhead-Mount Power Link 2000

Depending on configuration, wall and overhead-mount Power Link 2000s have one or two HV DCClosed High Voltage Direct Current Power Paths, named A and B. Each Power Path has two wire landings, an upper landing and a lower landing. Power Link 2000s with a single charging cable are configured with Power Path B landings only.

Power Link 2000 wall and overhead wire entry and landing

(a1) HV DCClosed High Voltage Direct Current Power Path A, upper landing

(a2) HV DCClosed High Voltage Direct Current Power Path A, lower landing

(b1) HV DCClosed High Voltage Direct Current Power Path B, upper landing

(b2) HV DCClosed High Voltage Direct Current Power Path B, lower landing

(c) LV DCClosed Low Voltage Direct Current

(d) Ethernet

(e) Ground

Wire Quantity, Size, and Termination

Following are wire specifications for the Power Link 2000, including the maximum quantity and size that the wire terminals can accommodate. All sizing assumes a maximum ambient temperature of 50 °C (122 °F). Where the maximum wire size is listed, the actual wire quantity and size must be chosen based on site-specific wiring requirements and in accordance with the maximum allowed conduit filling rate per local code.
Wire Specifications for Power Link 2000

Wire

Quantity

Size

Termination

HV DCClosed High Voltage Direct Current

Power Paths

A and B

(max. 500 A per landing)

Max. 12 wires per Power Path

(three wires per pole on each landing)

Upper landings:

Max. 150 mm2 (300 MCM)*

Lug: Long barrel and tongue with two holes spaced 44.5 mm (1.75 in) apart and sized for M12 studs.

Max. lug tongue width: 31 mm (1.25 in) for upper landings, 25.9 mm (1 in) for lower landings.

Aluminum lug max. tongue thickness: 10 mm (0.4 in) for upper landings, 5 mm (0.2 in) for lower landing.

Lower landings:

Max. 120 mm2 (4/0 AWGClosed American Wire Gauge)

Ground

Max. 6 wires

(one per Power Block)

Refer to the local code for size; max. 50 mm2 (1/0 AWGClosed American Wire Gauge)

Lug: Short barrel and tongue with single hole, sized for M6 stud.

LV DCClosed Low Voltage Direct Current

Max. 8 wires

(four wire pairs; each pair has one wire per pole)

16 mm2 (6 AWGClosed American Wire Gauge)

Stripped wire

Ethernet

Max. 4 cables

Outdoor-rated Cat6 STPClosed Shielded Twisted Pair***

RJ45 connector

Soft shutdown switch****

2 wires

2.5 mm2 (14 AWGClosed American Wire Gauge)

Stripped wire

*If utilizing both upper and lower landings, the maximum HV DCClosed High Voltage Direct Current wire size is 120 mm2 (4/0 AWGClosed American Wire Gauge).

***The required Ethernet cable type depends upon the cable run length. See the Express Plus Power Link 2000Site Design for details.

****Soft shutdown switch is an optional feature.

North American Wire, Voltage, and Current Ratings

North American Wire Specifications

 

Inputs to Power Block

Power Block to Each Power Link 2000

 

AC

and Ground

Shunt Trip

HV DCClosed High Voltage Direct Current

Output

48 V DC

Output

Ethernet

Circuit Voltage

480

V AC

240 V

100 -

1000 V

48 V

--

Max. Current

260 A

6 A

200,

250,

350, or

500 A

32 A

--

Notes

Rated for 600 V

L1, L2, L3,

Ground

 

Rated for 1000 V

Outdoor rated Cat6 STPClosed Shielded Twisted Pair or Paige GameChanger*

*The required Ethernet cable type depends upon the cable run length. See Ethernet requirements.

UK and European Wire, Voltage, and Current Ratings

UK and European Wire Specifications

 

Inputs to Power Block

Power Block to Each Power Link 2000

 

AC

and Ground

Shunt Trip

HV DCClosed High Voltage Direct Current

Output

48 V DC

Output

Ethernet

Circuit Voltage

400

V AC

< 240 V

200-

1000 V

48 V

--

Max. Current

315 A

6 A

200,

250,

350, or

500 A

32 A

--

Notes

3p+E

 

Rated for 1000 V

Outdoor rated Cat6 STPClosed Shielded Twisted Pair or Paige GameChanger*

* The required Ethernet cable type depends upon the cable run length. See Ethernet requirements.