Limit Per-Port Power Output
To limit per-port power output, complete the following steps:
-
Log in to ChargePoint Platform.
-
Navigate to Manage Energy > Shed/Restore.
-
Click the arrow ▷ beside your organization name to find the station or group of stations whose power output you want to limit or the arrow ▷ beside a station if you want to limit power output on just one port.
-
A green check mark in the Status column means the load control commands have been received by all the stations in the group.
-
Click Edit.
The Shed Load window opens.
-
Set a Duration.
-
Select one of the following forShed Mode:
-
Absolute Maximum Power per Port, specify the kW per port.
-
Relative Percent of Present Load, specify the percentage.
-
-
(Optional) Specify the date and time to start the Demand Response event.
-
Click the Start Time field to display a calendar to select the starting date.
-
Click the hh and mm drop-down lists to select the starting hour and minute.
Specifying a date and time is called Scheduled Demand Response and is not applied until the specified date and time; otherwise, it is called Immediate Demand Response.
-
-
Click Shed.
-
ChargePoint software instructs each station to reduce the power per your specified amount and time on a per-port basis.