Site Design Guidelines

This section describes general site design guidelines for Power Block and Power Link 1000.

Initial Site Guidelines

An onsite evaluation is needed to determine the wiring and conduit requirements from the electrical panel to the proposed parking spaces, as well as to measure cellular signal levels and identify suitable locations for any necessary cellular signal booster equipment.

If you have pre-existing infrastructure or are using your own preferred electrical contractor to prepare your site, an Express Plus Construction Signoff Form completed by a ChargePoint Operations and Maintenance (O&M) partner is required to certify compliance with electrical code and to ensure everything was prepared to ChargePoint specifications.

  • If the charging station is not installed, commissioned, or serviced by a ChargePoint Certified Technician using a ChargePoint-approved method, it is excluded from all ChargePoint and other warranties and ChargePoint is not responsible.
  • You must be a licensed electrician and complete the training at https://www.chargepoint.com/partners/training-certification to become ChargePoint certified and to access the ChargePoint web or app-based installer tools.

Plan for Future Charging Capacity

Designing electrical infrastructure to support current and future needs for EVClosed Electric Vehicle charging helps avoid costly upgrades later as demand for EVClosed Electric Vehicle charging grows.

Consider these methods to prepare a site for future charging stations in a later phase of work:

  • Add extra capacity if electrical panels are being upgraded now.

  • Use sub-panels as a way to shorten electrical paths.

  • Maximize the conduit and conductor sizes (to product specifications) between the main electrical panel and future stations to prevent needing to re-pull wires or trenching work if the site uses underground wiring.

  • Underground service wiring conduits can be pre-staged if the correct site construction is performed in advance. Allowed terminations include a distribution unit, junction box, or plugged conduit. This eases cable pulls for future stations.

System Placement

The placement of Power Link 1000 and Power Block must meet the following requirements:

Do not install Express Plus in a Class 1 hazardous location, as classified by NECClosed National Electric Code or local codes.

Site conditions must be compatible with the following specifications listed in the Express Plus Datasheet:

  • Operational altitude

  • Operating temperature

  • Operating humidity

  • Enclosure rating

To minimize costs, choose station locations that are close to the available electrical infrastructure. Selecting nearby locations help minimize long wire runs as well as any conduit or trenching work if the site uses underground wiring.

Express Plus components must be installed on a structure that is rated to support their weight. A level concrete base is recommended for Power Block and pedestal-mount product, and a flat wall or gantry for wall or overhead-mount product, respectively. Asphalt cannot support the full weight of Express Plus components. Failure to install the Express Plus components on a suitable structure may cause it to tip over, resulting in death, personal injury, or property damage.

Layout considerations:

  • Determine appropriate ground anchoring locations where concrete exists or can be installed (no asphalt surfaces).

  • Consider locations where it will be easy to add future stations.

  • If using conduits to pull wires, determine the best conduit layout to minimize linear conduit costs to multiple parking spaces. If possible, avoid or minimize trenching requirements, especially more costly trenching to run conduit under asphalt surfaces.

  • Determine if the existing utility service and electrical panel capacity is sufficient. Identify costs for any necessary upgrades and/or a new dedicated electrical panel. ChargePoint recommends using a licensed electrician to evaluate available capacity and identify any upgrades that may be required.

  • If a dedicated EVClosed Electric Vehicle electrical panel is required, choose a panel located close to the existing electrical supply.

  • Measure cellular signal levels to ensure adequate cellular coverage at the station locations. To ensure adequate signal strength in underground or enclosed parking structures, cellular repeaters may be required. For more information, see Connectivity.

  • ChargePoint recommends avoiding locations under trees where sap, pollen, or leaves would fall on the charging station and increase the station owner’s site maintenance workload.

Guidelines for Different Parking Arrangements

  • Choose adjacent parking spaces in an area with adequate lighting.

  • Consider how easily drivers can find the stations they need to access.

  • Check local requirements for accessibility and pathway width, sometimes called “path of travel”, to ensure that station placement does not restrict sidewalk use.

  • A pad built into the head of a parking space (instead of on the sidewalk) is allowed if local code allows it compared to the minimum parking space length, and the pad meets all pad requirements listed in this document.

Cable Reach

Cable Reach for standard, Tall and Overhead CMK

The maximum reach from the station to charge port on a typical vehicle is approximately 3.76 m (12 ft 4 in) (a) at a height of 0.6 m (2 ft) (b) above the ground.

The following table provides the maximum cable reach from the station to charge port on a vehicle:

The cable reach specifications for both the tall CMKClosed Cable Management Kit and overhead CMKClosed Cable Management Kit include the full extension of a tether cord from the CMKs, as depicted in the illustration above.

Cable Reach Specifications

 

Pedestal or wall-mount

product

Overhead-mount

product

CMKClosed Cable Management Kit

Standard CMKClosed Cable Management Kit

Tall CMKClosed Cable Management Kit

Overhead CMKClosed Cable Management Kit

Cable length

5.8 m (19 ft)

7.6 m (25 ft)

7.6 m (25 ft)

Cable reach

Horizontal or vertical reach

3.76 m (12 ft 4 in)

Horizontal (a)

6.09 m (20 ft)

Horizontal (c)

4.57 m (15 ft)
Vertical (d)

Height above ground

0.6 m (2 ft) (b)

Not applicable

IMPORTANT:

  • Diagonal stall parking is not recommended.

  • Place each product to maximize cable reach for the varied charge port locations on different EVs.

Commercial or Public Station Placement, Single or Dual Cable

For stall parking, ChargePoint recommends using perpendicular parking stalls that allow a vehicle to enter either front-first or rear-first, to better accommodate the varied locations of EVClosed Electric Vehicle charge ports.

While ChargePoint tests charging stations with a majority of upcoming vehicles, ChargePoint cannot guarantee the port locations of future vehicles and cannot warrant the configurations proposed will work for all vehicles.

This illustration depicts a charging station with a dual cable.

Single cable station centered configuration

  1. Cable reach radius: 3.76 m (12 ft 4 in)

The following three illustrations depict charging stations with single cables.

Commercial or public station placement cable range.

  1. Cable reach radius: 3.76 m (12 ft 4 in)

    Commercial or public station placement cable range.

  1. Cable reach radius: 3.76 m (12 ft 4 in)

Fleet Parking Arrangement

  • Stall parking (Dual Charge Cable): For installing dual charge cable Power Link 1000 stations, consider placing the station in front of every other parking space. Additionally, align the overhead CMKClosed Cable Management Kit tether with the parking stripes on either side of the charging station.

 

Stall dual charge cable parking configuration

Overhead CMK tether example

  • Stall parking (Single Charge Cable): Power Link 1000s with single charging cables are always configured with the charging cable on the right side of the enclosure. Align the overhead CMKClosed Cable Management Kit tether with the parking stall stripe adjacent to the vehicle's charging port. The illustrations below depict parking of the vehicles in relation to the charging stations, based on the side where the vehicle's charging port is located.

Vehicles with left-side charging ports Vehicles with right-side charging ports

Single charge cable with left-side charging ports

Single charge cable with right-side charging ports

  • Island parking: ChargePoint recommends placing a station in the center of the island facing away (station front is perpendicular to vehicles) in the same orientation. This allows the station to be accessible from both sides of the island.

 

Island parking  top down view

Island parking perpendicular orientation