Complete the Installation

To complete the installation, carry out the following steps:

Do not reconnect the power after completing the installation (after installing the covers). An Authorized Commissioning Partner will commission, power on, pinpoint, and configure Power Link 2000 after installation.

Seal Conduit Openings

To seal conduit openings, complete the following steps:

  1. Find the duct seal compound shipped with the Power Link 2000 (see Power Link 2000 Packages).

  2. Vacuum any residue around the conduits.

    Technical illustration depicts the procedural step.

  3. Torque the screws (x2) to 4.5 Nm (40 in-lb). The conduit sleeve must enclose the conduit opening space.

    Technical illustration depicts the procedural step.

  4. Use the duct seal compound and seal the space between the conduit sleeve and the bottom of the Power Link 2000 enclosure.

    Technical illustration depicts the procedural step.

Reinstall Rear Upper Cover

To reinstall the rear upper cover, complete the following steps:

Skip this section if rear upper cover was not removed.
  1. Align and seat cover onto the alignment pins (x2) on the frame.

    Technical illustration depicts the procedural step.

  2. Torque the screws (x6) to 4.5 Nm (40 in-lb).

    Technical illustration depicts the procedural step.

Reinstall Side Panels

To reinstall the side panels, complete the following steps:

Skip this section if side panels were not removed.
  1. Hold the charging cable up and place it into the cable way on the side panel.

    Technical illustration depicts the procedural step.

  2. Align and install the side panel onto the hooks (x2) and alignment pins (x2) on the frame.

    Technical illustration depicts the procedural step.

  3. Slowly slide the side panel down to engage the hooks (x2) on the frame.

    Technical illustration depicts the procedural step.

  4. Align the screw holes (x2) on the rear side of the side panel with the screws (x2) inside the lower enclosure and torque them to 4.5 Nm (40 in-lb).

    Technical illustration depicts the procedural step.

If two charging cables have been installed, repeat the procedure to install the other side panel.

Reinstall Cable Cap

To reinstall the cable cap, complete the following steps:

  1. Align and slide the cable cap down to reinstall.

    Technical illustration depicts the procedural step.

  2. If two charging cables have been installed, repeat for the other side.

 

Reinstall HV DC Input Bus Bar Safety Cover

Install cover onto the hooks (x2) and brackets (x2) and then slide it down.

Technical illustration depicts the procedural step.

Record MAC Address

Take a photograph of the Power Link 2000 activation QRClosed Quick Response code and MACClosed Message Authentication Code address, which can be found on the label affixed to the top of the Control and Communications Module (CCOMClosed Control and Communications Module). This information is used at Power Link 2000 setup.

Technical illustration depicts the procedural step.

Close Enclosure Doors

To close enclosure doors, complete the following steps:

  1. Disengage the door stopper (x1 per upper and lower enclosure door).

    Technical illustration depicts the procedural step.

  2. Quarter turn the door latches (x2 per upper and lower enclosure door).

    Technical illustration depicts the procedural step.

Install Front Upper Cover

To install the front upper cover, complete the following steps:

  1. Insert any one side of the cover into the groove on the side panel.

    Technical illustration depicts the procedural step.

  2. Gently flex the cover to insert its other side into the groove on the other side panel. At the same time, align and hook the ball studs (x3) behind the cover into the holes (x3) in a bracket on the upper door.

    Technical illustration depicts the procedural step.

  3. Alternatively, you can hold and flex the lower side of the cover slightly outward. While flexed, align the ball studs (x3) behind the cover with the holes (x3) in the bracket on the upper door and press in.

    Technical illustration depicts the procedural step.

  4. Make sure that the screws (x2) on the front upper cover are seated in their slots in the area light housing.

    Technical illustration depicts the procedural step.

Install Front Lower Cover

To install front lower cover, complete the following steps:

  1. Align top edge of the lower cover with the lower edge of the Control and Communication Module (CCOMClosed Control and Communications Module) trim.

    Technical illustration depicts the procedural step.

  2. While overlapped with the upper cover, insert any one side of the cover into the groove on the side panel.

    Technical illustration depicts the procedural step.

  3. Gently flex the cover to insert its other side into the groove on the other side panel. Make sure that the top and bottom corners of the cover are seated in the groove.

    Technical illustration depicts the procedural step.

  4. Press in below the holster trim and lower side of the cover; while pressed in, slide the cover down to engage the hooks (x2) behind the cover. See the previous step for the exact location of the hooks.

    Technical illustration depicts the procedural step.

  5. Make sure that the lower edge of the holster bracket and holster trim are aligned.

    Technical illustration depicts the procedural step.

  6. Place charging cable connectors into the holsters.

    Technical illustration depicts the procedural step.

Install Top Cap

To install the top cap, complete the following steps:

  1. Align the screws (x4) and install the top cap.

    • Front screws (x2)

      Technical illustration depicts the procedural step.

    • Rear screws (x2)

      Technical illustration depicts the procedural step.

  2. Make sure that the top cap sides are seated on edges on top of the side panels (x2).

    Technical illustration depicts the procedural step.

  3. Torque the rear screws (x2) to 2.8 Nm (25 in-lb) and front screws (x2) to 1.7 Nm (15 in-lb).

    Technical illustration depicts the procedural step.

Complete Recommended Checklist

Before leaving the installation site, complete the Variation B Pedestal-Mount Power Link 2000 Installation Checklist, available at ChargePoint Product Reference Documentation.

Provide the checklist and any spare parts (activation labels, and so on.) to the person responsible for activating the stations. This completes the installation of the Power Link 2000 charging station.