Introduction

This topic describes how to design an installation site for the ChargePoint® Express 250 DC fast charging station and install the Concrete Mounting Template, before station installation. An Express 250 charging station can be installed to operate by itself (called Standalone) or to share power with one other Express 250 for higher throughput (called Paired).

You must be a licensed electrician and complete online training to become a ChargePoint certified installer. If you do not complete training, you cannot access the ChargePoint network to complete installation. Find online training at: https://www.chargepoint.com/partners/training-certification. If the charging station is not installed by a ChargePoint certified installer, using a ChargePoint approved method, it is not covered under warranty and ChargePoint is not responsible for any malfunctions.

Accessing ChargePoint Documentation

Access documents at ChargePoint Product Reference Documentation.

ChargePoint Documentation

Document

Content

Primary Audiences

Datasheet

Full station specifications

Site designer, installer, and station owner

Site Design Guide

Civil, mechanical, and electrical guidelines to scope and construct the site

Site designer or engineer of record

Concrete Mounting Template Guide

Instructions to embed the charging station template in a concrete pad with anchor bolts and conduit placement (these may also be included in the Site Design Guide)

Site construction contractor

Surface Conduit Entry Kit Guide

Instructions for sites where conduit cannot be run underground

Installer

Construction Signoff Form

Checklists used by contractors to ensure the site is correctly completed and ready for product installation

Site construction contractor

Installation Guide

Anchoring, wiring, and powering on

Installer

Operation and Maintenance Guide

Operation and preventive maintenance information

Station owner, facility manager, and technician

Service Guide

Component replacement procedures, including optional components

Service technician

Declaration of Conformity

Statement of conformity with directives

Purchasers and public

Use low torque settings when working with power tools during installation or servicing. Over-torquing can damage the equipment.
Do not install or service the charging station in inclement weather. If you work in snow, rain, or wind, you must use a weather-proof shelter that covers all boxes and components.
For all charging station specifications other than dimensions and weights, refer to the product's Datasheet, which can be found online at ChargePoint Product Reference Documentation. For assistance, go to chargepoint.com/support and contact technical support using the appropriate region-specific number.

Installing the Express 250 requires two people and takes approximately 3-4 hours. This time estimate does not include the time needed to pull DC and Ethernet cable for a Paired installation if it is not already done. Paired installation also requires contacting a ChargePoint support technician to perform any required software updates and configuration.

Ensure that the installation complies with all applicable codes and ordinances.

Pairing Two Express 250s

If a CPE250 is installed with one Power Module and Power Select is used, then the station cannot be paired.

The Express 250 can be installed either as a standalone system, or paired with another Express 250 using a DC connection to more flexibly share load. The two Power Modules in the base of each charging station can be shared in any combination according to charging need. This allows high power output in sites with space constraints.

To pair two charging stations, all of the following are required:

  • Additional conduit, ducting, or armored cable (according to region) correctly installed between the two charging stations for DC conductors and Ethernet wiring

  • Both stations must have 62.5 kW power enabled (not allowed on stations only enabled for 50 kW)

  • Both stations must be provisioned for full power back to the panel (not allowed on power select stations)

Initial Site Guidelines

An onsite evaluation is needed to determine conduit and wiring requirements from the panel to the proposed parking spaces, as well as to measure cellular signal levels and identify suitable locations for any necessary cellular signal booster equipment.

If you have pre-existing infrastructure or are using your own preferred electrical contractor to prepare your site, a completed Construction Signoff Form is required to certify compliance with electrical specification requirements, and to ensure everything was prepared to ChargePoint specifications.

Always check local codes or consult an engineer to ensure the site is prepared in compliance with all applicable regulations. Local authorities might not allow a unit to operate if it is not installed to code.

Plan for Future Charging Capacity

ChargePoint recommends that you plan to install charging stations for 5-10% of parking spaces, or 10-15% for high EVClosed Electric Vehicle adoption areas like California. Designing electrical infrastructure to support current and future needs for EVClosed Electric Vehicle charging helps avoid costly later as demand for EVClosed Electric Vehicle charging grows.

Consider these methods to prepare a site for future charging stations in a later phase of work:

  • Add extra capacity if electrical panels are being upgraded now

  • Use sub-panels as a way to shorten electrical paths

  • Oversize the conduit between the main electrical panel and future stations

  • Install pull or junction boxes at the end of an existing row of charging stations, to ease cable pulls for future stations

  • If a junction box or disconnect will be installed between rows of stations, oversize the wiring between the main panel and the junction box to prevent needing to re-pull wire later

Charging Station Placement

To help minimize costs, choose station locations that are as close as possible to the available electrical infrastructure. Selecting these types of locations helps minimize long conduit and wire runs, as well as any trenching work.

The charging station must be installed on a level concrete base. Asphalt cannot support the full weight of the charging station. Failure to install on a level concrete base may cause the station to tip over, resulting in death, personal injury, or property damage.

The layout considerations are as follows:

  • Determine appropriate ground anchoring locations where concrete exists or can be installed (no asphalt surfaces).

  • Consider locations where it will be easy to add future stations.

  • Determine optimum conduit layout to minimize linear conduit costs to multiple parking spaces. If possible, avoid or minimize trenching requirements, especially more costly trenching to run conduit under asphalt surfaces.

  • Evaluate existing electrical infrastructure to determine if the existing utility service and electrical panel capacity is sufficient. Identify costs for any necessary upgrades and/or a new dedicated electrical panel. ChargePoint recommends using a certified electrician to evaluate available capacity and identify any upgrades that may be required.

  • If a dedicated EVClosed Electric Vehicle electrical panel is required, choose a panel location in close proximity to the existing electrical supply.

  • Measure cellular signal levels to ensure adequate cellular coverage at the station installation location. To ensure adequate signal strength in underground or enclosed parking structures, cellular repeaters may be required.

  • ChargePoint recommends to avoid locations under trees where sap, pollen, or leaves would fall on the charging station and increase the station owner’s site upkeep workload.

  • For stall parking, ChargePoint recommends using perpendicular parking stalls that allow a vehicle to enter either front-first or rear-first, to better accommodate the varied charge port locations on different EVs. Diagonal stall parking is not advised.

  • While ChargePoint tests charging stations with a majority of upcoming vehicles, ChargePoint cannot guarantee the port locations of future vehicles and cannot warrant the configurations proposed will work for all vehicles.
  • Choose adjacent parking spaces in an area with adequate lighting.

  • Consider how easily drivers can find the stations they need to access.

  • Check local requirements for accessibility and pathway width, sometimes called “path of travel”, to ensure station placement does not restrict sidewalk use.

  • Building a pad into the head of a parking space (instead of on the sidewalk) is allowed if a) local code allows it compared to the minimum parking space length, and b) the pad meets all pad requirements listed in this document.

  • Note that the station's two charge cables are different types of connectors to maximize usability across EVClosed Electric Vehicle models. The cables cannot both be used at the same time. Therefore, do not position an Express 250 to share two parking spots.

Place each charging station centered at the head of its parking space, with the touchscreen facing the vehicle. This placement maximizes cable reach for the varied charge port locations on different EVs.

  • Pull-through parking (gas station model) is not recommended. If pull-through parking is used, ChargePoint recommends placing at least one charging station on each side of the island. This avoids situations where the charging station is on the opposite side of the vehicle from the charge port. Guidance for station placement in island or curbside parking is shown below.

  1. Distance from left space marking: 3048 mm (120 in) maximum

  2. Distance from right space marking: 4876.8 mm (192 in)

  3. Distance from curb: 457.2 mm (18 in)

  4. Distance from curb: 457.2 mm (18 in)

  5. Example EVClosed Electric Vehicle length: 4978.4 mm (196 in)

  6. Recommended parking space length: 7924.8 mm (312 in)

  7. Recommended parking space width: 2743.2 mm (108 in)