CP4300W Installation
This document provides step-by-step instructions for installing a CP4300 Wall Mount ChargePoint® Networked Charging Station. Depending on the specific model of CP4300 you are installing, it may be a single port or dual port charging station.
Before You Begin
-
Ensure that all these conditions are met at the installation site:
-
The installation site is properly prepared and meets all conditions listed in the CP4000 Site Design Guide ( available at ChargePoint Product Reference Documentation).
-
The appropriate circuit protection and metering is in place, following local codes and regulations.
-
The mounting surface is smooth, stable, plumb, and strong. It provides sufficient stability for installing the charging station.
-
The electrical cable has been installed and about 2 m of cable is left for a service loop.
-
The electrical cable has a maximum diameter of 25 mm. The wire does not exceed 16 mm2.
-
The installation site is clean.
-
-
If you have not already done so, open Box #1 and locate the printed Quick Reference Guide. Review all safety information and heed all warnings listed in the guide.
-
Arrange for two people to complete the installation, due to the weight of the CP4300 and attached cables.
-
Do not place liquids, or objects containing liquids, on the charging station.
-
Do not place stickers, or other materials that may eliminate sufficient air circulation, on the charging station.
-
Only use accessories sold for the charging station by ChargePoint.
-
Review the CP4300 Datasheet (available at ChargePoint Product Reference Documentation).
-
Review the contents of this Installation Guide to familiarize yourself with the contents of each shipping box and the required installation steps. Follow the instructions in this guide and heed all warnings.
-
Tools and Materials
-
Cordless drill with a 10 mm masonry drill bit
-
Set of tamper-resistant Torx drivers (T20, T25, T27, T30)
-
Set of metric hex drivers 3 – 8 mm
-
Torque wrenches capable of measuring torques from 1 Nm - 175 Nm
-
#2 Phillips screwdriver
-
Electrical wire strippers
-
Crescent wrench, adjustable to 16 mm
-
Bent-nose pliers with 90 degree bend, 1.35 mm maximum tip diameter and 25 mm minimum opening
-
Spirit level, 40 cm length or shorter
-
Measuring tape
-
Utility knife or Dremel tool
-
Cable tie wraps
-
Electrical tape
-
Wire end ferrules—optional, to cover the stripped ends of flexible wires
-
Voltage meter
-
Cup for holding small parts
-
Damp cloth for wiping down the exterior of the station
-
Floor mat, padded ground covering, or other similar material to protect station components
-
Smartphone or laptop with a QR
Quick Response-code scanner, camera, and Internet connection
Summary of Shipping Boxes
The summary of shipping boxes are as follows:
|
Box # |
Assembly Name |
Overview of Box Contents |
|---|---|---|
|
1 |
CP4300 Charging Station Single Port or Dual Port |
|
|
2 |
Well Mount Kit |
|
|
3 |
Station Mount Kit |
|
|
4 |
Cable Management Kit |
|
|
5 |
Grounding Kit (United Kingdom only) |
|
A more detailed list of each box's contents is provided later in this guide.
Installation Sequence
Regardless of the specific type of CP4300 wall mount charging station, the high-level installation sequence is the same. Where this Installation Guide refers to two power cables or two station ports, the same instructions apply to single port stations.