Complete the Installation
To complete the installation, carry out all steps given below.
Verify and Adhere Ratings Label
-
Locate the ratings label and serial number on the back right edge of the heat sink.
-
Verify the ratings listed on the site drawing.
-
Choose the correct ratings label from the label sheet (included).
-
Adhere the label to the indentation.
Complete Recommended Checklist
Before leaving the installation site, complete the Power Link 1000 Installation Checklist, available at ChargePoint Product Reference Documentation.
Provide the checklist and any spare parts (activation labels, and so on.) to the person responsible for activating the stations. This completes the installation of the Power Link 1000 charging station.