Prepare for Installation

Follow the instructions provided in this topic to prepare Pantograph Down 2000 for installation.

Do not install or service the charging station in inclement weather. If you work in snow, rain, or wind, you must use a weather-proof shelter that covers all boxes and components.
Warranty Limitation
  • If the charging station is not installed, commissioned, or serviced by a ChargePoint certified technician using a ChargePoint-approved method, it is excluded from all ChargePoint and other warranties and ChargePoint is not responsible.
  • You must be a licensed electrician and complete training at https://www.chargepoint.com/partners/training-certification to become ChargePoint certified and to access ChargePoint's web-based installer tools or ChargePoint Installer app.
Ensure that the installation complies with all applicable codes and ordinances.
Keep components out of direct sunlight in a cool area until you install them.
Use low torque settings when working with power tools during installation or servicing. Over-torquing can damage the equipment.

 

 

Check Site Readiness

To check site readiness, complete this checklist before you install Pantograph Down 2000:

Site Readiness Checklist
Pantograph Down 2000 Site Readiness Checklist  
1. The electrical equipment is installed and labeled in accordance with the National Electrical Code (NECClosed National Electric Code) and all applicable requirements of the serving electric utility company and the authority having jurisdiction.
2. Power Blocks are installed at locations proposed in the site drawings.
3. The installation site for the Pantograph Down Mast meets the following requirements:
  • The concrete foundation was designed and approved by a structural engineer for the Pantograph Down Mast structural specifications given in the Pantograph Down 2000 Site Design Guide.

  • The concrete foundation is fully cured and smooth.

  • Anchor bolts (x4) are at locations proposed in the site drawings and installed per instructions given in the site plans.

  • Conduit stub-ups are present per the site plans.

  • Wires meet the requirements given in the site plans.

4. The installation site meets the drainage, ventilation guidelines, and clearances given in the Pantograph Down 2000 Site Design Guide.
5. Sufficient space is available to use a forklift or other lifting equipment, unpack, remove packing materials, and allow two people to freely move throughout the site.

Electrical Readiness

Refer to the Pantograph Down 2000 Datasheet and Pantograph Down 2000 Site Design Guide at ChargePoint Product Reference Documentation for electrical input and output specifications.

Bring These Tools and Resources

Pantograph Down 2000 requires at least three people for installing the mast and at least two people for installing all other components.

Additionally, the installer must bring the equipment, tools, and materials specified in this section. These are not provided by ChargePoint.

Comply with these guidelines to prevent component damage.
  • Use appropriately sized tools to torque fasteners.

  • Use the given torque values to tighten the fasteners.

  • Ensure that the tools such as torque tool, multimeter, and Ethernet tester are calibrated.

Equipment for Lifting and Installing Mast

Equipment for Lifting and Installing Mast

Orange and white icon that represents a tool or action.

Construction crane

  • Rated for ≥ 4536 kg (10,000 lb)

Orange and white icon that represents a tool or action.

Mobile elevating work platform (scissor lift)

Orange and white icon that represents a tool or action.

Metal lifting cable sling

  • Rated for ≥ 100 kg (220 lb)

  • Length 10 ft

Orange and white icon that represents a tool or action.

Flat eye web lifting sling (x2)

  • Rated for ≥ 2900 kg (6400 lb)

  • Length 3 m (10 ft)

Equipment for Lifting Enclosures and Pantograph

Equipment for Lifting Enclosures and Pantograph

Orange and white icon that represents a tool or action.

Forklift with anti-slip forks

  • Rated for ≥ 300 kg (661 lb)

  • Fork max size:

    • Width = 102–127 mm (4–5 in)

    • Thickness ≤ 57 mm (2.25 in)

  • If your site has height constraints or heights that exceed the service range of a forklift, use alternative equipment

 

 

Equipment and Tools for Installation

Equipment and Tools for Installation

Orange and white icon that represents a tool or action.Orange and white icon that represents a tool or action.

Paper towel roll

Orange and white icon that represents a tool or action.

Magnet tray

Orange and white icon that represents a tool or action.

Industrial vacuum cleaner

Orange and white icon that represents a tool or action.

Wire brush (to remove any residue on anchor bolts)

Orange and white icon that represents a tool or action.

Hard hat

Orange and white icon that represents a tool or action.

Cut-resistant gloves

Orange and white icon that represents a tool or action.

Safety glasses

Orange and white icon that represents a tool or action.

Ladder

Orange and white icon that represents a tool or action.

Cable ties

Orange and white icon that represents a tool or action.

Box cutter

Orange and white icon that represents a tool or action.

Cable puller or fish tape

Orange and white icon that represents a tool or action.

Measuring tape or other tool to measure height, length, and distance

Orange and white icon that represents a tool or action.

Level

Lockout/tagout equipment

Orange and white icon that represents a tool or action.

Multimeter (meter and probes rated for 1000 V)

Orange and white icon that represents a tool or action.

Ethernet tester such as a Klein Tools VDV526-052 VDV LANClosed Local Area Network Scout Jr. Tester or similar

Orange and white icon that represents a tool or action.

Conduit cutter (to cut up to 4 in conduits)

Orange and white icon that represents a tool or action.

Pliers

Orange and white icon that represents a tool or action.

  • Wire cutters, including Ethernet (Cat6 Shielded Twisted Pair (STPClosed Shielded Twisted Pair)) cable

  • Orange and white icon that represents a tool or action.

    Wire strippers, including Ethernet (Cat6 STPClosed Shielded Twisted Pair) cable

    Orange and white icon that represents a tool or action.

    Lug crimping tool and die

    Orange and white icon that represents a tool or action.

    Ethernet (RJ45) connector crimping tool

    Orange and white icon that represents a tool or action.

    Torque wrench

    Orange and white icon that represents a tool or action.

    Torque screwdriver

    Orange and white icon that represents a tool or action.

    Hex socket set (including 8 mm, 10 mm, 13 mm, 17 mm, 24 mm deep socket, 1/2 in, 9/16 in, 3/4 in, 7/16 in, 7/8 in, 15/16 in, 2-3/8 in, 3-1/2 in)

    Orange and white icon that represents a tool or action.

    Hex wrench (10 mm, 5/32 in, 3/16 in, 7/32 in, 7/16 in)

    Orange and white icon that represents a tool or action.

    Wrench set (including 3/4 in, 5/16 in, 13/16 in, 20 mm, 33 mm, 46 mm, and adjustable)

    3-1/2 in strike wrench

    Orange and white icon that represents a tool or action.

    Torx screwdriver (T20, T25, T30)

    Orange and white icon that represents a tool or action.

    T25 Security screwdriver

    Orange and white icon that represents a tool or action.

    Flathead screwdriver set (including 2.5 mm and 3.5 mm tip for terminal blocks)

    Orange and white icon that represents a tool or action.

    Phillips head screwdriver set (including #2)

    Orange and white icon that represents a tool or action.

    Torque paint pen

    Orange and white icon that represents a tool or action.

    Permanent marker

    Anti-oxidant joint compound (to make gastight joint between wire and lug) and wire pulling lubricant

    Orange and white icon that represents a tool or action.

    Weatherproof sealant

    Orange and white icon that represents a tool or action.

    Dielectric grease

    Orange and white icon that represents a tool or action.

    Hydraulic hole punch

    Orange and white icon that represents a tool or action.

    Rubber mallet

    Orange and white icon that represents a tool or action.

    Hand-held drill

    Orange and white icon that represents a tool or action.

    Drill bit (3/8 in)

    Orange and white icon that represents a tool or action.

    Smartphone with internet connectivity

    Orange and white icon that represents a tool or action.

    QRClosed Quick Response code scanner (usually built into the camera app)

    Orange and white icon that represents a tool or action.

    ChargePointInstaller app

    Orange and white icon that represents a tool or action.

    ChargePoint installer login credentials

    Additional Consumables

    The installer must provide the following parts. These parts are not provided by ChargePoint.

    • A 3-1/2 inch strut pipe strap (x1 per Pantograph Down Mast)

    • A water-tight cable gland for the ground wire that exits the Power Link 2000 bottom gland plate and connects to the Pantograph Down Mast (x1 per Power Link 2000)

    Wires and Terminations Required for Site

    The installer must bring all wires and lugs specified in this section. They are not provided by ChargePoint.

    • For AC and DC high voltage (HVClosed High Voltage), high current wiring, use copper or aluminum wires rated for 90 °C (194 °F).
    • For low voltage (LVClosed Low Voltage) DC wiring, use only copper wires (XHHW/XHHW-2 based on site condition, dry or wet) rated for 1000 V and 75 °C (167 °F).
    • For PD Controller 120–277 V AC input wires, use only copper wires rated for 600 V AC and 75 °C (167 °F).
    • Use copper lugs for copper wires and aluminum lugs for aluminum wires. The lugs must be nickel, tin, or silver plated compression (not mechanical) lugs. Nickel-plated lugs installed with dielectric grease is recommended.
    • All AC and DC high voltage wires must undergo insulation testing as outlined in the High Voltage Wire Insulation Resistance Test Field Guide.

    Mast-mount Power Link 2000 input wires

    The Power Block DC (HVClosed High Voltage and LVClosed Low Voltage) and Ethernet outputs are the inputs for the Power Link 2000. In some Express Plus architectures, the Power Link 2000 may receive DC (HVClosed High Voltage and LVClosed Low Voltage) power from Power Block(s) via a connection to another Power Link 2000. The Power Link 2000 may also be configured with LV DCClosed Low Voltage Direct Current connection with a soft shutdown switch and/or a hardwired Ethernet connection to a network server.

    Following are wire specifications for the Power Link 2000, including the maximum quantity and size that the wire terminals can accommodate. All sizing assumes a maximum ambient temperature of 50 °C (122 °F). Where the maximum wire size is listed, the actual wire quantity and size must be chosen based on site-specific wiring requirements and in accordance with the maximum allowed conduit filling rate per local code.
    Mast-mount Power Link 2000 Input Wire Specifications

    Input Wire

    Quantity

    Size

    Termination

    HV DCClosed High Voltage Direct Current

    (Max. 500 A per landing)

    Max. 12 wires

    (three per pole on each landing)

    Upper landings:

    Max. 150 mm2 (300 MCM)(*)

    Lug: Long barrel and tongue with two holes spaced 44.5 mm (1.75 in) apart and sized for M12 (0.5 in) studs.

    Max. tongue width: 31 mm (1.25 in) for upper landings, 25.9 mm (1 in) for lower landings.

    Aluminum lug max. tongue thickness: 10 mm (0.4 in) for upper landings, 5 mm (0.2 in) for lower landings.

    Lower landings:

    Max. 120 mm2 (4/0 AWGClosed American Wire Gauge)

    Ground

    (from Power Block)

     

    Max. 3 wires

    (one from each Power Block)

    Refer to local code for size;

    Max. 50 mm2 (1/0 AWGClosed American Wire Gauge)

    Lug: Short barrel and tongue with single hole and sized for M6 (0.25 in) stud.

    LV DCClosed Low Voltage Direct Current

    (from Power Block or another Power Link 2000)

    Max. 4 wires

    (two wire pairs; each pair has one wire per pole)

    16 mm2 (6 AWGClosed American Wire Gauge)

    Stripped wire end

    Ethernet

    Max. 4 cables

    Cat6 STPClosed Shielded Twisted Pair cable, outdoor rated or Paige OSP Shielded Gamechanger(**)

    RJ45 connector

    Soft shutdown switch(***)

    2 wires

    2.5 mm2 (14 AWGClosed American Wire Gauge)

    Stripped wire end

    (*) If utilizing both upper and lower landings, the maximum HV DCClosed High Voltage Direct Current wire size is 120 mm2 (4/0 AWGClosed American Wire Gauge). (**) The required Ethernet cable type depends upon the cable run length. See the Pantograph Site Design Guide for details. ( ***) Soft shutdown switch is an optional feature.

    Mast-mount Power Link 2000 output wires

    The mast-mount Power Link 2000 provides HV DCClosed High Voltage Direct Current output to one pantograph and provides LV DCClosed Low Voltage Direct Current and Ethernet output to the PD Controller. In some Express Plus architectures, the Power Link 2000 may provide DC (HVClosed High Voltage and LVClosed Low Voltage) power from Power Block(s) to other Power Link 2000(s).

    Following are wire specifications for the Power Link 2000, including the maximum quantity and size that the wire terminals can accommodate. All sizing assumes a maximum ambient temperature of 50 °C (122 °F). Where the maximum wire size is listed, the actual wire quantity and size must be chosen based on site-specific wiring requirements and in accordance with the maximum allowed conduit filling rate per local code.
    Mast-mount Power Link 2000 Output Wire Specifications

    Output Wire

    Quantity

    Size

    Termination

    HV DCClosed High Voltage Direct Current(*)

    6 wires

    (three per pole)

    120 mm2 (4/0 AWGClosed American Wire Gauge)

    Lug(**): Long barrel and tongue with two holes spaced 44.5 mm (1.75 in) apart and sized for M12 (0.5 in) studs.

    Max. tongue width: 31 mm (1.25 in).

    Aluminum lug max. tongue thickness: 5 mm (0.2 in).

    High power ground(*)

    (to pantograph PE)

    1 wire

    50 mm2

    (1/0 AWGClosed American Wire Gauge)

    Lug: Short barrel and tongue with single hole sized for M6 (0.25 in) stud.

    Ground

    (to Pantograph Down Mast)

    1 wire

    Refer to local code for size;

    Max. 50 mm2

    (1/0 AWGClosed American Wire Gauge)

    Lug: Short barrel and tongue with single hole sized for M6 (0.25 in) stud.

    LV DCClosed Low Voltage Direct Current

    (to another Power Link 2000)

    Max. 4 wires

    (two wire pairs; each pair has one wire per pole)

    16 mm2 (6 AWGClosed American Wire Gauge)

    Stripped wire end

    LV DCClosed Low Voltage Direct Current

    (to PD Controller)

    This wire pair is provided with the mast-mount Power Link 2000. The wire ships pre-terminated for connection within the Power Link 2000.

    Chassis ground

    (to PD Controller)

    1 wire

    4 mm2 (12 AWGClosed American Wire Gauge)

    Ring terminal: Sized for M6 (0.25 in) stud.

    Ethernet

    1 cable

    Cat6 STPClosed Shielded Twisted Pair cable, outdoor rated

    RJ45 connector, shielded

    (*) The output HV DCClosed High Voltage Direct Current and high power ground wires and conduit are provided with the Pantograph Down Mast. (**) Provided HV DCClosed High Voltage Direct Current wires are DLO copper wire, requiring flex lugs.

    PD Controller Wires

    Each PD Controller is configured with AC input from the site as well a LV DCClosed Low Voltage Direct Current, chassis ground, and Ethernet connection from a Power Link 2000. Allowed quantity, size, and terminations for these wires are listed below. Check the site plan for site specific wire specifications.

    Following are wire specifications for the PD Controller, including the maximum quantity and size that the wire terminals can accommodate. All sizing assumes a maximum ambient temperature of 50 °C (122 °F). Where the maximum wire size is listed, the actual wire quantity and size must be chosen based on site-specific wiring requirements and in accordance with the maximum allowed conduit filling rate per local code.
    PD Controller Wire Specifications

    Wire

    Quantity

    Size

    Termination

    120-277 V AC input

    2 wires

    (one per pole)

    Size based on branch circuit breaker;

    Max. 16 mm2 (6 AWGClosed American Wire Gauge)

    Stripped wire end

    AC ground

    1 wire

    Size based on branch circuit breaker;

    Max. 16 mm2 (6 AWGClosed American Wire Gauge)

    Stripped wire end

    LV DCClosed Low Voltage Direct Current input

    LV DCClosed Low Voltage Direct Current input wires are provided by ChargePoint for installing the PD Controller with the Pantograph Down Mast.

    Ethernet input

    See Power Link 2000 output wire specifications.

    RJ45 connector, unshielded

    Chassis ground

    See Power Link 2000 output wire specifications.

    Stripped wire end

    Schunk SLS 201.102 pantograph wires

    The Schunk SLS 201.102 pantograph is configured with HV DCClosed High Voltage Direct Current input and high power ground connection from a Power Link 2000. It also has a ground connection from the Pantograph Down Mast. Allowed quantity, size, and terminations for these wires are listed below. Check the site plan for site specific wire specifications.

    Following are wire specifications for the pantograph, including the maximum quantity and size that the wire terminals can accommodate. All sizing assumes a maximum ambient temperature of 50 °C (122 °F). Where the maximum wire size is listed, the actual wire quantity and size must be chosen based on site-specific wiring requirements and in accordance with the maximum allowed conduit filling rate per local code.
    Schunk SLS 201.102 unfurnished wire quantity, size, and termination specifications

    Wire

    Max. Wire Quantity and Size

    Termination

    HV DCClosed High Voltage Direct Current

    (from Power Link 2000)

    See Power Link 2000 output wire specifications.

    Lug: Single hole lug and sized for M10 bolt.

    High power ground (PE)

    (from Power Link 2000)

    See Power Link 2000 output wire specifications.

    Lug: Single hole lug and sized for M10 bolt.

    Ground

    (from Pantograph Down Mast)

    See Pantograph Down Mast wire specifications.

    Ring terminal: Sized for M8 bolt.

    Pantograph Down Mast wires

    The Pantograph Down Mast is configured with a ground connection from the Power Link 2000. Depending on site requirements, it may also be connected to a maximum of two grounding rods. Allowed quantity, size, and terminations for these wires are listed below. Check the site plan for site specific wire specifications.

    Following are wire specifications for the pantograph, including the maximum quantity and size that the wire terminals can accommodate. All sizing assumes a maximum ambient temperature of 50 °C (122 °F). Where the maximum wire size is listed, the actual wire quantity and size must be chosen based on site-specific wiring requirements and in accordance with the maximum allowed conduit filling rate per local code.
    Pantograph Down Mast Wire Specifications

    Wire

    Quantity

    Size

    Termination

    Ground

    (from grounding rods)

     

    Max. 2 wires

    Refer to local code for size;

    Max. 50 mm2 (1/0 AWGClosed American Wire Gauge)

    Lug: Single hole and sized for 3/8 in bolt.

    Ground

    (from Power Link 2000)

    1 wire

    See Power Link 2000 output wire specifications.

    Lug: Single hole and sized for 3/8 in bolt.

    Ground

    (to pantograph frame)

    1 wire

    Refer to local code for size;

    Max. 50 mm2 (1/0 AWGClosed American Wire Gauge)

    Ring terminal: Sized for M8 bolt.

    Tightening Torques

    Power Link 2000

    Power Link 2000 tightening torques
    Component Component Material Fastener Tool Torque

    Soft shutdown switch set screws

    2.5 mm flathead screwdriver

    0.6 Nm (5.3 in-lb)

    LV DC terminal set screws (for output to PD Controller)

    3.5 mm flathead screwdriver

    0.7 Nm (6.2 in-lb)

    LV DC terminal set screws (for output to Power Block or other Power Link 2000)

    3.5 mm flathead screwdriver

    1.5 Nm (13.3 in-lb)

    Gland plate screws

    Metal M5

    T25 Security

    4.5 Nm (40 in-lb)

    Ethernet to USB mounting nuts

    8 mm socket

    Enclosure mounting screws

    Metal

    M6

    T30 Torx

    5.6 Nm (50 in-lb)

    Ground wire lug nuts

    10 mm socket

    Chassis ground wire nuts

    HV DC wire lug nuts

    Metal

    M10

    17 mm socket

    19 Nm (14 ft-lb)

    Mounting base fasteners

    Metal 1/2 in 3/4 in socket 50 Nm (37 ft-lb)

    PD Controller

    PD Controller tightening torques
    Component Component Material Fastener Tool Torque

    Wi-Fi coaxial cable connector

    5/16 in wrench

    0.45 Nm (4 in-lb)

    RFID coaxial cable connector

    AC PE terminal set screw

    3.5 mm flathead screwdriver

    1.7 Nm (15 in-lb)

    AC circuit breaker set screws (18-12 AWG wires)

    #2 Phillips screwdriver

     

    2.4 Nm (21.2 in-lb)

    AC circuit breaker set screws (10-8 AWG wires)

    2.8 Nm (24.8 in-lb)

    AC circuit breaker set screws (6 AWG wires)

    4 Nm (35.4 in-lb)

    3/4 in NPT cable gland cap

    33 mm wrench

     

    4.5 Nm (40 in-lb)

     

    1-1/4 in NPT cable gland cap

    46 mm wrench

     

    3/4 in NPT cable gland nut

    33 mm wrench

     

    7.9 Nm (70 in-lb)

    1-1/4 in NPT cable gland nut

    46 mm wrench

    10.2 Nm (90 in-lb)

    Enclosure mounting bolts

    Metal 5/16 in 1/2 in socket 10 Nm (90 in-lb)

    Unistrut mounting fasteners

    Metal 1/2 in 3/4 in socket 50 Nm (37 ft-lb)

    Auxiliary Components

    Auxiliay components tightening torques
    Component Component Material Fastener Tool Torque

    Wi-Fi antenna coaxial cable connector

    13/16 hex wrench

     

    1.5 Nm (13.3 in-lb)

    RFID antenna coaxial cable connector

    Status LED mounting nuts

    Metal

    M5

    8 mm socket

    4.5 Nm (40 in-lb)

     

     

    Auxiliary component frame, side cover nuts (at cover ends)

    Metal

    Auxiliary component frame, front cover

    Metal

    M6

    10 mm socket

    5.6 Nm (50 in-lb)

     

     

     

    Wi-Fi and RFID antenna assembly mounting nuts

    Metal

    Auxiliary component frame, ground wire fasteners

    Metal

    Auxiliary component frame, rear cover

    Metal

    Auxiliary component frame, side cover nuts (along cover length)

    Metal

    Auxiliary component frame, side rail mounting nuts

    Metal

    M16

    24 mm deep socket

    94.9 Nm (70 ft-lb)

    Schunk SLS 201.102 Pantograph

    Schunk SLS 201.102 pantograph tightening torques
    Component Component Material Fastener Tool Torque

    Pantograph mounting rail clamp screw

    7/16 in 4.7 Nm (42 in-lb)

    Control pilot cable gland

    20 mm wrench

    1.5 Nm (13.3 in-lb)

    Pantograph frame ground wire fasteners

    Metal

    M8

    13 mm socket

    12.2 Nm (108 in-lb)

    HV DC wire fasteners

    Metal M10 13 mm and 17 mm socket 19 Nm (14 ft-lb)

    Pantograph mounting fasteners

    Metal 5/8 in 15/16 in socket 99 Nm (73 ft-lb)

    Pantograph Down Mast

    Schunk SLS 201.102 pantograph tightening torques
    Component Component Material Fastener Tool Torque

    Mast covers and panels screws

    (for pantograph access cover, hinge access cover, mast arm endcap, and vent panels)

    Metal 3/8 in 7/32 in hex 5.6 Nm (50 in-lb)

    Mesh screen screws

    Metal M6 T25 Torx and 10 mm socket 5.6 Nm (50 in-lb)

    Ground wire (inside of mast arm) fasteners

    Metal M8 13 mm socket 15 Nm (133 in-lb)

    Ground bar base fasteners

    Metal 3/8 in 9/16 in socket 19 Nm (14 ft-lb)

    Ground bar wire fasteners

    Mast arm fasteners

    Metal 1-1/2 in 2-3/8 in socket Turn of Nut Technique

    Mast mounting nuts

    Metal 2-1/4 in 3-1/2 in strike wrench

    Pantograph Down 2000 Packages

    Component crates are heavy and can cause injury or death if dropped. Do not stand or walk beneath the crate while it is being lifted. Take precautions against the crate tipping or sliding.

    Leave components in the shipping crate until needed. When removing, protect them from damage (such as scratches) by placing them flat on a blanket or tarp, face up. Do not stand up cover panels, as they may be knocked or blown over. Cover charging connectors to prevent damage or ingress.

    Keep components out of direct sunlight in a cool area until you install them.
    Always transport and store components in their original packaging. Use appropriate lifting equipment (forklift or crane, lifting straps, and any corresponding attachments and accessories). Ensure the load rating of all lifting equipment is adequate for the weight of the crated components.
    Keep components in original packaging, free of moisture, and protected from damage until you install or service them at the site. Store all shipments of components in a dry covered location and protect from moisture.

    For any missing component, contact chargepoint.com/support.

    Package Dimensions and Weights

    Package Dimensions and Weights
    Package Dimensions (LxWxH) Max. Weight

    Pantograph Down Mast

    Varies. The mast arrives on a flat bed truck.

    3175 kg (7000 lb)

    Mast installation parts crate

    0.9 x 0.68 x 0.47 m

    (35.5 x 27 x 18.5 in)

    113 kg (250 lb)

    Mast panels and covers crate

    0.86 x 0.74 x 0.55 m

    (34 x 29.3 x 21.5 in)

    113 kg (250 lb)

    Mast Components Kit

    Not available

    Not available

    Power Link 2000

    1.52 x 1.14 x 0.51 m

    (60 x 45 x 20 in)

    182 kg (400 lb)

    PD Controller

    0.8 x 0.79 x 0.33 m

    (31.5 x 31 x 13 in)

    37 kg (81 lb)

    Schunk SLS 201.102

    2.44 x 1.22 x 1.22 m

    (96 x 48 x 48 in)

    340 kg (750 lb)

    Schunk SLS 201.102 Auxiliary Components Kit

    2.71 x 0.93 x 0.34 m

    (106.8 x 36.3 x 13.3 in)

    75 kg (165 lb)

    Ethernet to USBClosed Universal Serial Bus Kit (option)

    0.3 x 0.39 x 0.22 m

    (11.81 x 15.35 x 8.66 in)

    1.4 kg (3 lbs)

    Pantograph Down Mast

    The Pantograph Down Mast ships to site on a flatbed truck, along with two parts crates.

    1. Mast

    2. Installation parts crate

    3. Panels and covers crate

    Installation Parts Crate

    Images are not exact to scale.

    1. Power Link 2000 mounting base

    2. PD Controller mounting unistruts (x2)

    3. Mast ground bar

    4. Knockout cover

    5. Knockout cover wedge pins (x2)

    6. Pivot hinge plugs (x2)

    1. Bags with fasteners and hardware:

      • Fasteners for securing mast arm to pole: 1-1/2 x 8 in bolts (x10), 1-1/2 in washers (x20), 1-1/2 in nuts (x10)

      • Fasteners for securing Power Link 2000 mounting base: 1/2 in bolts (x6), 1/2 in washer (x6), 1/2 in nuts (x6)

      • Fasteners for securing Power Link 2000 to mounting base: M6 x 25 mm screws (x8)

      • Fasteners for securing PD Controller mounting unistruts: 1/2 in bolts (x4), 1/2 in washers (x4), 1/2 in nuts (x4)

      • Fasteners for securing PD Controller to unistruts: 5/16 x 1-1/4 in bolts (x4), 5/16 in washers (x4), 5/16 in spring nuts (x4)

      • Fasteners for securing Schunk SLS 201.102 pantograph on mast: 5/8 x 2 in bolt (x4). 5/8 in flat washer (x4), 5/8 in lock washer (x4), 5/8 in hex nut (x4)

      • Fasteners for securing mast ground bar: 3/8 x 1-1/4 in bolts (x2), 3/8 in flat washers (x4), 3/8 in dragon tooth washers (x4), 3/8 in lock washers (x2), 3/8 in hex nuts (x2)

      • Lanyards (x3) with caribiner clips attached at each end

      • Fasteners for securing mast covers and panels: 3/8 x 1-1/4 in button head screws (x16)

     

    Panels and Covers Crate

    Images are not exact to scale.

    1. Upper vent panels (x2)

    2. Lower rear vent panel

    3. Hinge top access cover

    4. Arm end cap

    5. Pantograph top access cover

    Mast Components Kit

    Power Link 2000 Package

    PD Controller Package

    Schunk SLS 201.102 Package

    The pantograph ships crated and secured on a pallet.

    Schunk SLS 201.102 Auxiliary Components Kit

    The Auxiliary Components Kit package ships on a pallet.

    Labeled diagram of product, tools or parts.

    1. Mounting frame side cover, right

    2. Mounting frame rail, right

    3. Mounting frame side cover, left

    4. Mounting frame rail, left

    5. RFIDClosed Radio Frequency IDentification antenna assembly

    6. Status LED and cable

    7. Mounting frame cover, front

    8. Controller interface cable (5 m, 16.4 ft)

    9. Mounting frame cover, rear

    1. Wi-FiClosed Wireless Fidelity and RFIDClosed Radio Frequency IDentification antenna coaxial cables (x2) (5m, 16.4 ft each)

    2. Hardware box with:

      • Ground wire (0.5 m, 1.6 ft)

      • M8 bolt and M8 nut (x1 each)

      • M10 bolts and M10 flange nuts (x5 each)

      • M16 bolts and M16 nuts (x4 each)

      • Wire terminal operating tool

      • Cable ties (x9)

    3. Wi-FiClosed Wireless Fidelity antenna assembly

     

    Disconnect Power

    To disconnect power, complete the following steps:

    Risk of shock
    • Before any procedure, disconnect the power.
    • Follow local code and site lockout/tagout procedure to de-energize the station.
    • Wait for energy to dissipate (approximately five minutes).
    • Keep power off until all covers and panels are reinstalled and the work is complete.
    Failure to follow these instructions can result in serious injury, loss of life, or property damage.
    1. Disconnect power at the site electrical panel.

      Follow standard practice and local code to de-energize the applicable circuit and lock out/tag out the disconnect before proceeding.

      Technical illustration depicts the procedural step.

    2. Use a multimeter to test that the unit is de-energized.