Prepare for Installation
This section describes how to prepare for the installation.
Check Site Readiness
Power Block can be installed on either a newly poured pad or an existing concrete surface. Power Block also supports wiring run above ground for locations where no underground wiring access exists (such as parking garages) or where underground junction boxes are not permitted.
Before beginning work, check that the site meets these civil and mechanical requirements:
|
Express Plus Power Block Pre-Installation Checklist |
|||||
|---|---|---|---|---|---|
|
Each Power Block concrete pad has either a site drawing approved by a structural engineer for this specific site, or an existing concrete pad that has been approved by a structural engineer for the Power Block’s dimensions and weight. |
☐ |
|||
|
Each concrete pad must be fully cured and smooth, and must not exceed a slope of approximately 20 mm per meter (0.25 in per ft). |
☐ |
|||
|
Each Power Block pad must conform to the design requirements listed in the Express Plus Site Design Guide. |
||||
|
Wires and conduits meet the requirements given in the site drawings. |
☐ | |||
|
Walls, fences, or slopes must not prevent water from draining from the pad. |
☐ |
|||
|
You have sufficient space around the installation pad to use a forklift and other lifting equipment, unpack crates, remove packing materials, and allow two people to freely move throughout the area. |
☐ |
|||
Remove any concrete that is not level with the rest of the surface so you can level the components. Use a grinder or a hammer and chisel to remove any bumps in the concrete.
Electrical Readiness
If the site does not meet these basic requirements, contact ChargePoint before continuing.
-
The appropriate circuit protection and metering is in place at the installation site.
-
A grounding conductor that complies with local codes is properly grounded to earth at the service equipment or, when supplied by a separate system, at the supply transformer.
-
A correctly rated, dedicated breaker is installed for each Power Block:
|
Nominal Voltage |
Input Current Rating |
Branch Circuit Capacity and Breaker |
Breaker Size |
|---|---|---|---|
|
Europe: 400 V |
315 A |
350 A or 400 A |
400 A |
|
North America: 480 V |
260 A |
350 A or 400 A |
-
Breakers have shunt trip capability (if specified) to each Power Block.
-
All necessary electrical infrastructure has been completed per local codes and ChargePoint specifications for 3-phase power plus ground, with properly sized wire at the station.
Neutral is not required for system operation, however Neutral-to-ground bonding is required at the Main Distribution Panel (MDP) supplying the charging station.This requirement is applicable to installations carried out within the province of Québec, Canada. Whether using a step-up or step-down autotransformer, refer to the 'Hydro-Québec bulletin - Choosing the right one 600/480 V transformer', that is publicly available, for specific guidance. -
All High Voltage wires (AC and DC) are required to go through Insulation Resistance Testing. The completed test report with measurements is to be available for review (upon request) prior to Commissioning of the Charger.
Refer to the Express Plus High Voltage Wire Insulation Resistance Test Field Guide to find out about the steps to be taken and the Insulation Resistance Test Measurements that are required for the AC and DC wires.
-
Wi-Fi
Wireless Fidelity and cellular signal strength meet the requirements stated in the Express Plus Power Block and Power Link Site Design Guide.
For questions about site specifications, refer to the Express Plus Datasheet andExpress Plus Power Block and Power Link Site Design Guide.
Pedestal-Mount Specifications
Power Block must be installed on either a newly poured concrete pad embedded with the Concrete Mounting Template (CMT) or on an existing concrete surface using the Surface Conduit Entry (SCE
Surface Conduit Entry) kit.
IMPORTANT:
-
The concrete surface must be smooth and cannot exceed a slope of 20 mm per meter (1/4 inch per foot). If an existing concrete surface does not meet the slope requirement, a localized concrete pad must be poured and leveled to meet the slope requirement.
-
Stub-up entry of wires laid underground is the most common installation method. Surface entry of wires laid above ground is allowed only at sites where the wires cannot be laid underground such as in a parking garage. Contact ChargePoint for the Surface Conduit Entry (SCE
Surface Conduit Entry) Kit, which includes the hardware needed to install on an existing concrete surface.
Concrete Pad Specifications
The concrete pad for the Power Block must either be designed to be site-specific or must meet the specifications provided below. In some extreme conditions, a larger pad may be required. For sites with less stringent seismic, soil, or wind conditions, a smaller pad might be possible.
Conservative stability specifications for the Power Block are listed below for the following design scenarios:
-
170 mph wind, high seismic, Class 3 Soil
-
170 mph wind, high seismic, Class 4 Soil
-
170 mph wind, high seismic, Class 5 Soil
-
140 mph wind, lower seismic, Class 3 Soil
-
140 mph wind, lower seismic, Class 4 Soil
-
140 mph wind, lower seismic, Class 5 Soil
All scenarios assume:
-
Minimum concrete rating of 2500 PSI.
-
All-threaded M16 anchor bolts are embedded 229 mm (9 in) into the concrete pad, and are made of ASTM F1554 Grade 55 carbon steel and hot dip galvanized (HDG
Hot Dipped Galvanized). -
The anchor bolts placement is centered within the designed stability area.
|
Design Scenarios |
Pad Width |
Pad |
#N1 @ S1” O.C. |
#N2 @ S2” O.C. |
|
|---|---|---|---|---|---|
|
1 |
1753 mm |
1753 mm |
457 mm |
#4 @ 305 mm (12 in) O.C. |
#4 @ 305 mm (12 in) O.C. |
|
2 |
1753 mm |
1753 mm |
686 mm |
#4 @ 152 mm (6 in) O.C. |
#4 @ 152 mm (6 in) O.C. |
|
3 |
1524 mm |
1524 mm |
457 mm |
#4 @ 305 mm (12 in) O.C. |
#4 @ 305 mm (12 in) O.C. |
|
4 |
1524 mm |
1524 mm |
457 mm |
#4 @ 305 mm (12 in) O.C. |
#4 @ 305 mm (12 in) O.C. |
|
5 |
1524 mm |
1524 mm |
457 mm |
#4 @ 305 mm (12 in) O.C. |
#4 @ 305 mm (12 in) O.C. |
|
6 |
1524 mm |
1524 mm |
457 mm |
#4 @ 305 mm (12 in) O.C. |
#4 @ 305 mm (12 in) O.C. |
Wires Entry - Stub up
For stub-up wiring:
-
The Power Block must mount onto four M16 anchor bolts exposed 76 mm (3 in) above the concrete pad.
-
The Concrete Mounting Template (CMT) of Power Block must be embedded into a newly poured concrete pad to align anchor bolts and underground run stub up wiring conduits or armored cables.
The CMT of Power Block
is shipped separately, and
must be assembled onsite before pouring the concrete pad.
-
In regions that use conduits, the conduits must not have bell ends. Conduits with bell ends may interfere with tolerances inside the Power Block and Power Link.
-
Conduits must be stub-up to the following height from the concrete pad surface.
-
Power Block: 559 – 914 mm (22 – 36 in)
-
Power Link: 102 – 160 mm (4 – 6-1/4 in)
-
Concrete Mounting Template
The Power Block Concrete Mounting Template (CMT) facilitates wires entry or exit (through conduits or armored cables), and anchor bolt locations.
-
M16 anchor bolt (x2) locations for mounting SCE
Surface Conduit Entry gland plate (applicable only for >surface entry of wires). -
M16 anchor bolt (x4) locations 76 mm (3 in) above concrete for mounting Power Block.
-
HV DC
High Voltage Direct Current output B wires exit. -
HV DC
High Voltage Direct Current output A wires exit.The DC output of Power Block is the DC input for the Power Link.
-
AC input wires entry.
-
LV DC
Low Voltage Direct Current output, shunt trip wires, and Ethernet cable exit.-
One for shunt trip (if used).
-
Three for LV
Low Voltage wires and Ethernet cable.
-
In regions that use conduits, the conduits must be laid per the conduit layout defined by the Concrete Mounting Template (CMT) and the outer diameter of conduits must not exceed the trade sizes listed below. In regions that do not use conduits and/or use armored cables, the cables may be laid per the conduit layout defined by the CMT.
The CMT must be embedded with its top panel positioned 51 mm (2 in) below the concrete surface.
The CMT should already be embedded in the concrete pad, unless the site is using surface-conduit entry. Verify the AC and DC conduits are positioned correctly.
The following table provides the maximum size and quantity of conduits that can be installed on Power Block:
|
Conduits For |
Conduit Quantity x Trade Size |
|
|---|---|---|
|
North America |
Europe |
|
|
HV DC |
2 x 4 inch max. |
2 x 110 mm max. |
|
AC input wires |
1 x 4 inch max. |
1 x 110 mm max. |
|
LV |
4 x 1 inch max. |
4 x 25 mm max. |
The actual conduit size and quantity must be chosen based on site-specific wiring requirements.
For wire specifications, refer to the Express Plus Power Block and Power Link Site Design Guide.
Required Tools and Materials
Installing the Power Block requires at least two people. Additionally, the installer must bring the following tools and materials. These are not provided by ChargePoint.
- Use tools suitable to torque metric fasteners. All fasteners used are in metric sizes.
- Use the given torque values to tighten the fasteners.
- Ensure that the tools such as torque tool, multimeter, and Ethernet tester are calibrated.
|
|
Forklift
|
||
|
|
Stepladder |
|
Lock out/tag out equipment |
|
|
Hard hat |
|
Cut-resistant gloves |
|
|
Safety glasses |
|
Head lamp |
|
|
Measuring tape or other tool to measure height, length, and distance |
|
Level |
|
|
Use hand to tighten |
|
Box cutter |
|
|
Phillips screwdriver set
|
|
Flat head screwdriver |
|
|
Torx wrench set
|
|
Torx security wrench
|
|
|
Torque wrenches for 4 to 95 Nm (3 to 70 ft-lb) |
|
Adjustable wrench |
|
|
Socket wrench set including deep sockets, up to 25 mm |
|
Cable puller or fish tape |
|
|
Hydraulic hole punch tool (to cut 4 inch holes in gland plate) |
|
Conduit cutters (to cut up to 4 inch conduits) |
|
|
Multimeter with Cat III 1000 V ratings, such as Fluke 87V or similar |
|
Ethernet tester such as a Klein Tools VDV526-052 VDV LAN |
|
|
Wire strippers, including Ethernet (Cat6 STP |
|
Ethernet (RJ45) connector crimping tool |
|
|
Wire cutters, including Ethernet (Cat6 STP |
|
Lug crimping tool |
|
|
Dielectric grease |
|
Torque paint pen |
|
|
Cable ties |
|
Permanent marker |
|
|
Isopropyl wipes and towel roll |
|
Duct seal compound |
|
|
Coolant funnel Two gallon coolant |
|
Padlock provided by station owner if required (for security panel on Power Block) |
|
|
Wire brush (to remove concrete from bolts) |
|
Broom and vacuum |
|
|
Smartphone with: Internet connectivity |
|
ChargePoint installer login credentials |
|
|
QR |
|
Exact location of stations or units, including parking space |
|
|
Ferrule crimp tool (for 16 mm2 or 6 AWG |
||
Tightening Torque
| Component (x Fastener Quantity) | Component Material | Fastener | Tool | Torque |
|---|---|---|---|---|
| Metal | M16 | 24 mm deep socket |
54 Nm (40 ft-lb) |
|
|
Metal |
M16 |
24 mm deep socket |
95 Nm (70 ft-lb) |
| Metal | M10 |
15 mm socket |
19 Nm (168 in-lb) |
|
|
Metal |
M12 |
18 mm socket |
21 Nm (15.5 ft-lb) |
|
|
Metal |
M10 |
15 mm socket |
19 Nm (14 ft-lb) |
|
|
Metal |
M12 |
19 mm socket |
21 Nm (15.5 ft-lb) |
|
Metal |
M10 |
15 mm socket |
19 Nm (14 ft-lb) |
|
|
Metal |
M6 |
T30 Torx |
7.0 Nm (62 in-lb) |
|
| Metal | M6 | T30 Torx | 7.0 Nm (62 in-lb) |
Materials
|
|
|
|
|
|
|
Check Express Plus Shipping Crates
Express Plus ships in multiple crates. Ensure you have all components at the installation site.
The crate is heavy and can cause injury or death if dropped. Do not stand or walk beneath the crate while it is being lifted. Take precautions against the crate tipping or sliding.
Leave components in the shipping crate until needed. When removing, protect them from damage (such as scratches) by placing them flat on a blanket or tarp, face up. Do not stand up cover panels, as they may be knocked or blown over. Cover charging connectors to prevent damage or ingress.
IMPORTANT: Keep components out of direct sunlight in a cool area until you install them.
| Components | Contents in Boxes and Pallets |
|---|---|
|
Power Block
|
Power Block unit(s)
|
| Power Block Pedestal |
|
| Power Block Pallet |
Power Block Pallet: The following ships in 6 Boxes:
|
| Power Module |
|
|
Installation Kit |
|
| Power Block Surface Conduit Entry (SCE |
|
| Concrete Mounting Template (CMT) (Optional) |
|
General Estimates for Lifting
| Component | Dimensions (L x W x H) | Max. Weight |
|---|---|---|
|
Power Block Crate |
1.18 x 1.14 x 2.04 m (46.5 x 45 x 80.25 in) |
475 kg (1048 lbs) |
|
Power Block Pedestal Box |
1.12 x 0.978 x 0.762 m (44 x 38.5 x 30 in) |
57 kg (125 lbs) |
|
Power Block Pallet |
1.22 x 1.22 x 1.36 m (48 x 48 x 53.5 in) |
163 kg (360 lbs) |
|
Power Module Box NOTE: A Power Block can use up to five Power Modules, which ship in separate pallets. |
0.902 x 0.572 x 0.375 m (35.5 x 22.5 x 14.75 in) |
41.28 kg (91 lbs) |
|
Power Block Surface Conduit Entry Kit (Option) Box |
1.05 x 0.245 x 0.524 m (41.38 x 9.63 x 20.63 in) |
13.88 kg (30.6 lbs) |
|
Concrete Mounting Template (CMT) (Option) Box |
1.08 x 0.127 x 0.873 m (42.63 x 5.00 x 34.38 in |
26 kg (57 lbs) |
|
CMT (Option) Pallet NOTE:
|
1.22 x 1.02 x 1.22 m (48 x 40 x 48 in) |
227 kg (500 lbs) |
Disconnect Power
To disconnect power, complete the following steps:
- Before any procedure, disconnect the power.
- Follow local code and site lockout/tagout procedure to de-energize the station.
- Wait for energy to dissipate (approximately five minutes).
- Keep power off until all covers and panels are reinstalled and the work is complete.
-
Disconnect power at the site electrical panel.
Follow standard practice and local code to de-energize the applicable circuit and lock out/tag out the disconnect before proceeding.
-
Use a multimeter to test that the unit is de-energized.