Prepare for Installation
This topic describes how to prepare for the installation.
Check Site Readiness
Power Block can be installed on either a newly poured pad or an existing concrete surface. Power Block also supports wiring run above ground for locations where no underground wiring access exists (such as parking garages) or where underground junction boxes are not permitted.
Before beginning work, check that the site meets these civil and mechanical requirements:
|
Express Plus Power Block Pre-Installation Checklist |
|||||
|---|---|---|---|---|---|
|
Each concrete pad must be fully cured and smooth, and must not exceed a slope of approximately 20 mm per meter (0.25 in per ft). |
☐ |
|||
|
The concrete pad or concrete surface meets the mounting specifications given in the Express Plus Power Block and Power Link Site Design Guide and/or is inspected and approved by a structural engineer for the dimensions and weights (as given in the Site Design Guide) of the Power Block and its Power Modules. |
☐ | |||
|
Walls, fences, or slopes must not prevent water from draining from the pad. |
☐ |
|||
|
You have sufficient space around the installation pad to use a forklift and other lifting equipment, unpack crates, remove packing materials, and allow two people to freely move throughout the area. |
☐ |
|||
Power Block Readiness
Concrete Mounting Template (CMT)
The Power Block Concrete Mounting Template (CMT) should already be embedded in the concrete pad, unless the site is using a surface-conduit entry. Verify the AC and DC conduits are positioned correctly.
-
M16 anchor bolt (x2) locations for mounting SCE
Surface Conduit Entry gland plate (applicable only for >surface entry of wires). -
M16 anchor bolt (x4) locations 76 mm (3 in) above concrete for mounting Power Block.
-
HV DC
High Voltage Direct Current output B wires exit. -
HV DC
High Voltage Direct Current output A wires exit.The DC output of Power Block is the DC input for the Power Link.
-
AC input wires entry.
-
LV DC
Low Voltage Direct Current output, shunt trip wires, and Ethernet cable exit.-
One for shunt trip (if used).
-
Three for LV
Low Voltage wires and Ethernet cable.
-
In regions that use conduits, the conduits must be laid per the conduit layout defined by the Concrete Mounting Template (CMT) and the outer diameter of conduits must not exceed the trade sizes listed below. In regions that do not use conduits and/or use armored cables, the cables may be laid per the conduit layout defined by the CMT.
The Concrete Mounting Template CMT must be embedded with its top panel positioned 51 mm (2 in) below the concrete surface.
The following table provides the maximum size and quantity of conduits that can be installed on Power Block:
|
Conduits For |
Conduit Quantity x Trade Size |
|
|---|---|---|
|
North America |
Europe |
|
|
HV DC |
2 x 4 inch max. |
2 x 110 mm max. |
|
AC input wires |
1 x 4 inch max. |
1 x 110 mm max. |
|
LV |
4 x 1 inch max. |
4 x 25 mm max. |
The actual conduit size and quantity must be chosen based on site-specific wiring requirements.
For wire specifications, see the Express Plus Power Block and Power Link Site Design Guide.
Clearances
The Power Block requires minimum site and service clearances.
Image not to scale.
| Power Block | Clearance |
|---|---|
|
610 mm (24 in) recommended (for rear service access) |
|
1000 mm (39.3 in) |
|
51 mm (2 in) |
General Estimates for Lifting
| Component | Dimensions (L x W x H) | Max. Weight |
|---|---|---|
|
Power Block Crate |
1.18 x 1.14 x 2.04 m (46.5 x 45 x 80.25 in) |
475 kg (1048 lbs) |
|
Power Block Pedestal Box |
1.12 x 0.978 x 0.762 m (44 x 38.5 x 30 in) |
57 kg (125 lbs) |
|
Power Block Pallet |
1.22 x 1.22 x 1.36 m (48 x 48 x 53.5 in) |
163 kg (360 lbs) |
|
Power Link 1000 Box |
2.34 x 0.97 x 0.58 m (92.25 x 38.13 x 22.75 in) |
385.6 kg (850 lbs) |
|
Power Module Box NOTE: A Power Block can use up to five Power Modules, which ship in separate pallets. |
0.902 x 0.572 x 0.375 m (35.5 x 22.5 x 14.75 in) |
41.28 kg (91 lbs) |
|
Power Block Surface Conduit Entry Kit (Option) Box |
1.05 x 0.245 x 0.524 m (41.38 x 9.63 x 20.63 in) |
13.88 kg (30.6 lbs) |
|
Concrete Mounting Template (CMT) (Option) Box |
1.08 x 0.127 x 0.873 m (42.63 x 5.00 x 34.38 in |
26 kg (57 lbs) |
|
CMT (Option) Pallet NOTE:
|
1.22 x 1.02 x 1.22 m (48 x 40 x 48 in) |
227 kg (500 lbs) |
Electrical Readiness
If the site does not meet these basic requirements, contact ChargePoint before continuing.
-
The appropriate circuit protection and metering is in place at the installation site.
-
A grounding conductor that complies with local codes is properly grounded to earth at the service equipment or, when supplied by a separate system, at the supply transformer.
-
A correctly rated, dedicated breaker is installed for each Power Block:
|
Nominal Voltage |
Input Current Rating |
Branch Circuit Capacity and Breaker |
Breaker Size |
|---|---|---|---|
|
Europe: 400 V |
315 A |
350 A or 400 A |
400 A |
|
North America: 480 V |
260 A |
350 A or 400 A |
-
Breakers have shunt trip capability (if specified) to each Power Block.
-
All necessary electrical infrastructure has been completed per local codes and ChargePoint specifications for 3-phase power plus ground, with properly sized wire at the station.
Neutral is not required for system operation, however Neutral-to-ground bonding is required at the Main Distribution Panel (MDP) supplying the charging station.This requirement is applicable to installations carried out within the province of Québec, Canada. Whether using a step-up or step-down autotransformer, refer to the 'Hydro-Québec bulletin - Choosing the right one 600/480 V transformer', that is publicly available, for specific guidance.
For questions about site specifications, refer to the Express Plus Datasheet and Express Plus Power Block and Power Link Site Design Guide.
Required Tools and Materials
Installing the Power Block requires at least two people. Additionally, the installer must bring the following tools and materials. These are not provided by ChargePoint.
|
|
Forklift
|
||
|
|
Stepladder |
|
Lock out/tag out equipment |
|
|
Hard hat |
|
Cut-resistant gloves |
|
|
Safety glasses |
|
Head lamp |
|
|
Measuring tape or other tool to measure height, length, and distance |
|
Level |
|
|
Use hand to tighten |
|
Box cutter |
|
|
Phillips screwdriver set
|
|
Flat head screwdriver |
|
|
Torx wrench set
|
|
Torx security wrench
|
|
|
Torque wrenches for 4 to 95 Nm (3 to 70 ft-lb)
Only for tool balancer: 3 mm spanner wrench |
|
Adjustable wrench |
|
|
Socket wrench set including deep sockets, up to 25 mm |
|
Cable puller or fish tape |
|
|
Hydraulic hole punch tool (to cut 4 inch holes in gland plate) |
|
Conduit cutters (to cut up to 4 inch conduits) |
|
|
Multimeter with Cat III 1000 V ratings, such as Fluke 87V or similar |
|
Ethernet tester such as a Klein Tools VDV526-052 VDV LAN |
|
|
Wire strippers, including Ethernet (Cat6 STP |
|
Ethernet (RJ45) connector crimping tool |
|
|
Wire cutters, including Ethernet (Cat6 STP |
|
Lug crimping tool |
|
|
Die electric grease |
|
Torque paint pen |
|
|
Cable ties |
|
Permanent marker |
|
|
Isopropyl wipes and towel roll |
|
Duct seal compound |
|
|
Coolant funnel Two gallon coolant |
|
Padlock provided by station owner if required (for security panel on Power Block) |
|
|
Wire brush (to remove concrete from bolts) |
|
Broom and vacuum |
|
|
Smartphone with: Internet connectivity |
|
ChargePoint installer login credentials |
|
|
QR |
|
Exact location of stations or units, including parking space |
|
|
Ferrule crimp tool (for 16 mm2 or 6 AWG |
||
Tightening Torque
| Component (x Fastener Quantity) | Component Material | Tool | Torque |
|---|---|---|---|
| Metal | 24 mm deep socket |
54 Nm (40 ft-lb) |
|
|
Metal |
24 mm deep socket |
95 Nm (70 ft-lb) |
| Metal |
15 mm socket |
19 Nm (168 in-lb) |
|
|
Metal |
18 mm socket |
21 Nm (15.5 ft-lb) |
|
|
Metal |
15 mm socket |
19 Nm (14 ft-lb) |
|
|
Metal |
19 mm socket |
21 Nm (15.5 ft-lb) |
|
Metal |
15 mm |
19 Nm (14 ft-lb) |
|
|
Metal |
T30 Torx |
7.0 Nm (62 in-lb) |
|
| Metal | T30 Torx | 7.0 Nm (62 in-lb) |
Materials
|
|
|
|
|
|
|
|
Check Express Plus Shipping Crates
Express Plus ships in multiple crates. Ensure you have all components at the installation site.
Refer to the Power Link Installation Guide for the list of Power Link crates. This section lists shipping crates for Power Block.
Leave components in the shipping crate until needed. When removing, protect them from damage (such as scratches) by placing them flat on a blanket or tarp, face up. Do not stand up cover panels, as they may be knocked or blown over. Cover charging connectors to prevent damage or ingress.
|
Power Block |
|
|
Power Module |
|
|
Installation Kit |
|