Prepare for Installation

This section describes how to prepare for the installation.

Check Site Readiness 

Power Block can be installed on either a newly poured pad or an existing concrete surface. Power Block also supports wiring run above ground for locations where no underground wiring access exists (such as parking garages) or where underground junction boxes are not permitted.

If not installed correctly, the ChargePoint charging station may pose a fall hazard, leading to death, personal injury, or property damage. Always use the provided Concrete Mounting Template shown preinstalled here, or a ChargePoint approved surface mounting solution, to install the ChargePoint charging station. Always install in accordance with applicable codes and standards using licensed professionals. Non approved installation methods are performed at the risk of the contractor and void the Limited One-Year Parts Exchange Warranty.

Before beginning work, check that the site meets these civil and mechanical requirements:

Power Block Pre-Installation Checklist

Express Plus Power Block Pre-Installation Checklist

1.  

Each Power Block concrete pad has either a site drawing approved by a structural engineer for this specific site, or an existing concrete pad that has been approved by a structural engineer for the Power Block’s dimensions and weight.

2.  

Each concrete pad must be fully cured and smooth, and must not exceed a slope of approximately 20 mm per meter (0.25 in per ft).

3.  

Each Power Block pad must conform to the design requirements listed in the Express Plus Site Design Guide.

 
4.  

Wires and conduits meet the requirements given in the site drawings.

5.  

Walls, fences, or slopes must not prevent water from draining from the pad.

6.  

You have sufficient space around the installation pad to use a forklift and other lifting equipment, unpack crates, remove packing materials, and allow two people to freely move throughout the area.

Remove any concrete that is not level with the rest of the surface so you can level the components. Use a grinder or a hammer and chisel to remove any bumps in the concrete.

Electrical Readiness

If the site does not meet these basic requirements, contact ChargePoint before continuing.

  • The appropriate circuit protection and metering is in place at the installation site.

  • A grounding conductor that complies with local codes is properly grounded to earth at the service equipment or, when supplied by a separate system, at the supply transformer.

  • A correctly rated, dedicated breaker is installed for each Power Block:

Power Block Breaker Table

Nominal Voltage

Input Current Rating

Branch Circuit Capacity and Breaker

Breaker Size

Europe: 400 V

315 A

350 A or 400 A

400 A

North America: 480 V

260 A

350 A or 400 A

  • Breakers have shunt trip capability (if specified) to each Power Block.

  • All necessary electrical infrastructure has been completed per local codes and ChargePoint specifications for 3-phase power plus ground, with properly sized wire at the station.
    Neutral is not required for system operation, however Neutral-to-ground bonding is required at the Main Distribution Panel (MDP) supplying the charging station.

    This requirement is applicable to installations carried out within the province of Québec, Canada. Whether using a step-up or step-down autotransformer, refer to the 'Hydro-Québec bulletin - Choosing the right one 600/480 V transformer', that is publicly available, for specific guidance.
  • All High Voltage wires (AC and DC) are required to go through Insulation Resistance Testing. The completed test report with measurements is to be available for review (upon request) prior to Commissioning of the Charger.

    Refer to the Express Plus High Voltage Wire Insulation Resistance Test Field Guide to find out about the steps to be taken and the Insulation Resistance Test Measurements that are required for the AC and DC wires.

  • Wi-FiClosed Wireless Fidelity and cellular signal strength meet the requirements stated in the Express Plus Power Block and Power Link Site Design Guide.

For questions about site specifications, refer to the Express Plus Datasheet andExpress Plus Power Block and Power Link Site Design Guide.

Pedestal-Mount Specifications

Power Block must be installed on either a newly poured concrete pad embedded with the Concrete Mounting Template (CMT) or on an existing concrete surface using the Surface Conduit Entry (SCEClosed Surface Conduit Entry) kit.

IMPORTANT:

  • The concrete surface must be smooth and cannot exceed a slope of 20 mm per meter (1/4 inch per foot). If an existing concrete surface does not meet the slope requirement, a localized concrete pad must be poured and leveled to meet the slope requirement.

  • Stub-up entry of wires laid underground is the most common installation method. Surface entry of wires laid above ground is allowed only at sites where the wires cannot be laid underground such as in a parking garage. Contact ChargePoint for the Surface Conduit Entry (SCEClosed Surface Conduit Entry) Kit, which includes the hardware needed to install on an existing concrete surface.

If not installed correctly, the ChargePoint charging station may pose a crushing hazard, leading to death, personal injury, or property damage. Always use the Concrete Mounting Template specified in this document section, or a ChargePoint-approved surface mounting solution, to install the ChargePoint charging station. Always install in accordance with applicable codes and standards using licensed professionals. Non-approved installation methods are performed at the risk of the contractor and void the Limited One-Year Parts Exchange Warranty.

Concrete Pad Specifications

The concrete pad for the Power Block must either be designed to be site-specific or must meet the specifications provided below. In some extreme conditions, a larger pad may be required. For sites with less stringent seismic, soil, or wind conditions, a smaller pad might be possible.

Conservative stability specifications for the Power Block are listed below for the following design scenarios:

  1. 170 mph wind, high seismic, Class 3 Soil

  2. 170 mph wind, high seismic, Class 4 Soil

  3. 170 mph wind, high seismic, Class 5 Soil

  4. 140 mph wind, lower seismic, Class 3 Soil

  5. 140 mph wind, lower seismic, Class 4 Soil

  6. 140 mph wind, lower seismic, Class 5 Soil

All scenarios assume:

  • Minimum concrete rating of 2500 PSI.

  • All-threaded M16 anchor bolts are embedded 229 mm (9 in) into the concrete pad, and are made of ASTM F1554 Grade 55 carbon steel and hot dip galvanized (HDGClosed Hot Dipped Galvanized).

  • The anchor bolts placement is centered within the designed stability area.

Power Block Concrete Pad Specifications

Design Scenarios

Pad

Width

Pad
Thickness

#N1 @ S1” O.C.
Top Rebar

#N2 @ S2” O.C.
Bottom Rebar

1

1753 mm
(69 in)

1753 mm
(69 in)

457 mm
(18 in)

#4 @ 305 mm (12 in) O.C.

#4 @ 305 mm (12 in) O.C.

2

1753 mm
(69 in)

1753 mm
(69 in)

686 mm
(27 in)

#4 @ 152 mm (6 in) O.C.

#4 @ 152 mm (6 in) O.C.

3

1524 mm
(60 in)

1524 mm
(60 in)

457 mm
(18 in)

#4 @ 305 mm (12 in) O.C.

#4 @ 305 mm (12 in) O.C.

4

1524 mm
(60 in)

1524 mm
(60 in)

457 mm
(18 in)

#4 @ 305 mm (12 in) O.C.

#4 @ 305 mm (12 in) O.C.

5

1524 mm
(60 in)

1524 mm
(60 in)

457 mm
(18 in)

#4 @ 305 mm (12 in) O.C.

#4 @ 305 mm (12 in) O.C.

6

1524 mm
(60 in)

1524 mm
(60 in)

457 mm
(18 in)

#4 @ 305 mm (12 in) O.C.

#4 @ 305 mm (12 in) O.C.

Wires Entry - Stub up

For stub-up wiring:

  • The Power Block must mount onto four M16 anchor bolts exposed 76 mm (3 in) above the concrete pad.

  • The Concrete Mounting Template (CMT) of Power Block must be embedded into a newly poured concrete pad to align anchor bolts and underground run stub up wiring conduits or armored cables.

    The CMT of Power Block

    is shipped separately, and

    must be assembled onsite before pouring the concrete pad.

  • In regions that use conduits, the conduits must not have bell ends. Conduits with bell ends may interfere with tolerances inside the Power Block and Power Link.

  • Conduits must be stub-up to the following height from the concrete pad surface.

    • Power Block: 559 – 914 mm (22 – 36 in)

    • Power Link: 102 – 160 mm (4 – 6-1/4 in)

Concrete Mounting Template

The Power Block Concrete Mounting Template (CMT) facilitates wires entry or exit (through conduits or armored cables), and anchor bolt locations.

Power Block Concrete Mount Template
  1. M16 anchor bolt (x2) locations for mounting SCEClosed Surface Conduit Entry gland plate (applicable only for >surface entry of wires).

  2. M16 anchor bolt (x4) locations 76 mm (3 in) above concrete for mounting Power Block.

  3. HV DCClosed High Voltage Direct Current output B wires exit.

  4. HV DCClosed High Voltage Direct Current output A wires exit.

    The DC output of Power Block is the DC input for the Power Link.

  5. AC input wires entry.

  6. LV DCClosed Low Voltage Direct Current output, shunt trip wires, and Ethernet cable exit.

    • One for shunt trip (if used).

    • Three for LVClosed Low Voltage wires and Ethernet cable.

In regions that use conduits, the conduits must be laid per the conduit layout defined by the Concrete Mounting Template (CMT) and the outer diameter of conduits must not exceed the trade sizes listed below. In regions that do not use conduits and/or use armored cables, the cables may be laid per the conduit layout defined by the CMT.


The CMT must be embedded with its top panel positioned 51 mm (2 in) below the concrete surface.

The CMT should already be embedded in the concrete pad, unless the site is using surface-conduit entry. Verify the AC and DC conduits are positioned correctly.

The following table provides the maximum size and quantity of conduits that can be installed on Power Block:

Power Block Stub-up Conduit Specifications

Conduits For

Conduit Quantity x Trade Size

North America

Europe

HV DCClosed High Voltage Direct Current output wires

2 x 4 inch max.

2 x 110 mm max.

AC input wires

1 x 4 inch max.

1 x 110 mm max.

LVClosed Low Voltage DC, shunt trip, and Ethernet output wires

4 x 1 inch max.

4 x 25 mm max.

The actual conduit size and quantity must be chosen based on site-specific wiring requirements.

For wire specifications, refer to the Express Plus Power Block and Power Link Site Design Guide.

Required Tools and Materials

Installing the Power Block requires at least two people. Additionally, the installer must bring the following tools and materials. These are not provided by ChargePoint.

Comply with these guidelines to prevent component damage.
  • Use tools suitable to torque metric fasteners. All fasteners used are in metric sizes.
  • Use the given torque values to tighten the fasteners.
  • Ensure that the tools such as torque tool, multimeter, and Ethernet tester are calibrated.

Forklift

  • Rated for ≥ 680 kg (1500 lb)

  • Maximum size of forklift tines:

    • Width = 102–127 mm (4–5 in)

    • Maximum thickness ≤ 57 mm (2.25 in)

  • If your site has height constraints, use alternative equipment

Stepladder

Lock out/tag out equipment

Hard hat

Cut-resistant gloves

Safety glasses

Head lamp

Measuring tape or other tool to measure height, length, and distance

Level

Use hand to tighten

Box cutter

Phillips screwdriver set

  • #2 Phillips screwdriver with long handle

  • #3 Phillips screwdriver

  • #5 Phillips screwdriver

  • Right angle (90°) #5 Phillips screwdriver

Flat head screwdriver

Torx wrench set

  • T20 (only for tool balancer)

  • T25

  • T30

Torx security wrench

  • T25

Torque wrenches for 4 to 95 Nm (3 to 70 ft-lb)

Adjustable wrench

Socket wrench set including deep sockets, up to 25 mm

Cable puller or fish tape

Hydraulic hole punch tool (to cut 4 inch holes in gland plate)

Conduit cutters (to cut up to 4 inch conduits)

Multimeter with Cat III 1000 V ratings, such as Fluke 87V or similar

Ethernet tester such as a Klein Tools VDV526-052 VDV LANClosed Local Area Network Scout Jr. Tester or similar

Orange and white icon that represents a tool or action.

Wire strippers, including Ethernet (Cat6 STPClosed Shielded Twisted Pair) cable

Ethernet (RJ45) connector crimping tool

  • Wire cutters, including Ethernet (Cat6 STPClosed Shielded Twisted Pair) cable

  • Lug crimping tool

    Dielectric grease

    Torque paint pen

    Cable ties

    Permanent marker

    Isopropyl wipes and towel roll

    Duct seal compound

    Coolant funnel

    Two gallon coolant

    Padlock provided by station owner if required (for security panel on Power Block)

    Wire brush (to remove concrete from bolts)

    Broom and vacuum

    Smartphone with: Internet connectivity

    ChargePoint installer login credentials

    QRClosed Quick Response code scanner (usually built into the camera app)

    Exact location of stations or units, including parking space

    Ferrule crimp tool (for 16 mm2 or 6 AWGClosed American Wire Gauge wire)    

     


    Tightening Torque

    Tightening Torques
    Component (x Fastener Quantity) Component Material Fastener Tool Torque
    Metal M16 24 mm deep socket

    54 Nm (40 ft-lb)

    Metal

    M16

    24 mm deep socket

    95 Nm (70 ft-lb)

    Metal M10

    15 mm socket

    19 Nm (168 in-lb)

    Metal

    M12

    18 mm socket

    21 Nm (15.5 ft-lb)

    Metal

    M10

    15 mm socket

    19 Nm (14 ft-lb)

    Metal

    M12

    19 mm socket

    21 Nm (15.5 ft-lb)

    Metal

    M10

    15 mm socket

    19 Nm (14 ft-lb)

    Metal

    M6

    T30 Torx

    7.0 Nm (62 in-lb)

    Metal M6 T30 Torx 7.0 Nm (62 in-lb)

    Materials

    • AC and ground conductors as required by site drawings

    • DC conductors as required by site drawings

    • 48 V DC wiring as required by site drawings

    • Shunt trip wiring (if on site drawings)

    • Power Block DC and AC lugs:

      • Plated copper compression lugs (not mechanical)

      • Must fit M12 stud size

      • Must fit 44.5 mm (1.75 in) hole spacing

      • 2-hole specified for North America only

      • Single hole is only permitted in Europe

      • Maximum tongue width ≤ 50.8 mm (2 in)

      Check site drawings for quantity of lugs.

    • RJ45 shielded connectors

    Check Express Plus Shipping Crates

    Express Plus ships in multiple crates. Ensure you have all components at the installation site.

    The crate is heavy and can cause injury or death if dropped. Do not stand or walk beneath the crate while it is being lifted. Take precautions against the crate tipping or sliding.

    Always transport and store the charging components in their original packaging. Use appropriate lifting equipment (forklift or crane, lifting straps, and any corresponding attachments and accessories). Ensure the load rating of all lifting equipment is adequate for the weight of the crated components.
    Keep components in original packaging, free of moisture, and protected from damage until you install or service them at the site. Store all shipments of components in a dry covered location and protect from moisture.

    Leave components in the shipping crate until needed. When removing, protect them from damage (such as scratches) by placing them flat on a blanket or tarp, face up. Do not stand up cover panels, as they may be knocked or blown over. Cover charging connectors to prevent damage or ingress.

    IMPORTANT: Keep components out of direct sunlight in a cool area until you install them.

    Shipping Crate Contents
    Components Contents in Boxes and Pallets

    Power Block

     

    Power Block unit(s)

    • Enclosure (upper and lower cabinets pre-assembled together)

      • Lower heat exchanger (dry box hex)

        This ships in a box inside the lower cabinet of the enclosure.

    • Fuses

    • Doors and covers

      • Lower door preinstalled

    Power Block Pedestal
    • Power Block Pedestal

    • Bolts and nuts

    • Gland plates (x2)

    • Upper covers - Front and Rear Pedestal

    Power Block Pallet

    Power Block Pallet: The following ships in 6 Boxes:

     

    • Box 1: DC Fuse Kits

      • Make sure to install the PB amperage sticker that is included in this box

      • Fuses either (x4) or (x2)

      • See the DC Fuse Kits section for Images and details on two types of configuration


    • Box 2:

      • T-25 screws for Pedestal Covers

      • Coolant

    • Box 3:

      • 4 Side Covers

      • Top Cover

    • Box 4: Front and Back Upper Covers

    • Box 5: Front Lower and Middle Covers

    • Box 6: Back Lower and Middle Covers

     

    Power Module
    • Up to five per Power Block

    Installation Kit

    • Duct seal compound

    • Propylene glycol coolant

      The coolant label references its Material Safety Datasheet.

    • T25 Torx security screwdriver

    • Coolant funnel

    Power Block Surface Conduit Entry (SCEClosed Surface Conduit Entry) (Optional)
    Concrete Mounting Template (CMT) (Optional)
    • CMT

    • Bolts and fasteners

    Lower heat exchanger and each Power Module are heavy. Two people are needed to install these components.

    General Estimates for Lifting

    Estimates for Lifting
    Component Dimensions (L x W x H) Max. Weight

    Power Block Crate

    1.18 x 1.14 x 2.04 m

    (46.5 x 45 x 80.25 in)

    475 kg

    (1048 lbs)

    Power Block Pedestal Box

    1.12 x 0.978 x 0.762 m

    (44 x 38.5 x 30 in)

    57 kg

    (125 lbs)

    Power Block Pallet

    1.22 x 1.22 x 1.36 m

    (48 x 48 x 53.5 in)

    163 kg
    (360 lbs)

    Power Module Box

    NOTE: A Power Block can use up to five Power Modules, which ship in separate pallets.

    0.902 x 0.572 x 0.375 m

    (35.5 x 22.5 x 14.75 in)

    41.28 kg

    (91 lbs)

    Power Block Surface Conduit Entry Kit (Option) Box

    1.05 x 0.245 x 0.524 m

    (41.38 x 9.63 x 20.63 in)

    13.88 kg

    (30.6 lbs)

    Concrete Mounting Template (CMT) (Option) Box

    1.08 x 0.127 x 0.873 m
    (42.63 x 5.00 x 34.38 in
    26 kg
    (57 lbs)

    CMT (Option) Pallet

    NOTE:

    • 8 cartons per pallet

    • Single unit can be stacked onto one of the System-PB1000-PDK for shipping.

    1.22 x 1.02 x 1.22 m

    (48 x 40 x 48 in)

    227 kg

    (500 lbs)

    Disconnect Power

    To disconnect power, complete the following steps:

    Risk of shock
    • Before any procedure, disconnect the power.
    • Follow local code and site lockout/tagout procedure to de-energize the station.
    • Wait for energy to dissipate (approximately five minutes).
    • Keep power off until all covers and panels are reinstalled and the work is complete.
    Failure to follow these instructions can result in serious injury, loss of life, or property damage.
    1. Disconnect power at the site electrical panel.

      Follow standard practice and local code to de-energize the applicable circuit and lock out/tag out the disconnect before proceeding.

      Technical illustration depicts the procedural step.

    2. Use a multimeter to test that the unit is de-energized.