Power Off

To power off, complete the following steps:

Required Tools and Materials

 

Multimeter (meter and probes rated for 1000 V)

 

Lockout/tagout equipment

Power Off

You must be a ChargePoint Certified Technician to power off the charging station, or warranty limitations apply.

  1. An Express Plus configuration can have one or more Power Blocks connected to one or more Power Link 1000s in what is called a cluster. Refer to the site's single line diagram (SLD) and identify the following:

    • All Power Blocks and/or Power Link 1000s to be serviced.

    • All Power Link 1000s within the same cluster as the products identified above.

  2. End all charging sessions on all Power Link 1000s identified in step above.

    Failure to end the charging session before beginning service could damage hardware components. Such damaged components may need to be replaced.
  3. Determine where to disconnect the high voltage (HVClosed High Voltage) power. Refer to the site's SLD and identify the location of control elements such as circuit breakers and disconnect switches.

    Technical illustration depicts the procedural step.

    1. Transformer configuration

    2. Ground connection

    3. Electrical panel

    4. Circuit breakers

    5. AC disconnect switch (optional)

    6. Maintenance switch (optional)

    Methods for HVClosed High Voltage power disconnect fall into two categories:

    • Category 1 - Remove AC power from connected Power Blocks using one of the following methods:

      • At the site electrical panel, turn the circuit breaker (d) switch to the OFF position to power off all Power Blocks and Power Link 1000s downstream of the breaker.

      • If an AC disconnect switch has been installed between Power Block and the site electrical panel, turn the AC disconnect switch (e) to the OFF position to power off all Power Blocks and Power Link 1000s downstream of the AC disconnect switch.

    • Category 2 - Turn the maintenance switch (f)  to the OFF position.

      • This power off option is available only if the Power Link 1000 is equipped with a maintenance switch within its lower enclosure.
      • This power off option de-energizes HVClosed High Voltage components in the upper enclosure.
  4. Wait for energy to dissipate (approximately five minutes).

Check Power Block Status Light

Skip this step if the Power Link 1000 was powered off by maintenance switch.
  1. Open the security panel to check the status light.

    Open the security panel to check the status light

  2. The status light must be off (unlit). If the status light is on (glowing any color), do not proceed further with servicing. Wait the required time for energy to dissipate.

When you power on, the status light should turn on (light up yellow). If the light is red, contact ChargePoint at chargepoint.com/support.

Disconnect HV Power in Power Link 1000

  1. Remove charging cable connectors off the Power Link 1000 and place it on a soft padded surface.

  2. Determine if the Power Link 1000 has preassembled covers or unassembled components, remove them as necessary.

  3. Open the lower door.

  4. Pull the maintenance switch to OFF position.

    • Do not remove the lower bus bar safety cover (cover on the maintenance switch) without disconnecting power at the site electrical panel or AC disconnect switch. The bus bars and HV DCClosed High Voltage Direct Current input wires connected below the maintenance switch are still energized.
    • Unless you disconnect power at the site electrical panel, all other connected Power Link 1000s will still be powered on and energized.
    • Do not touch the HVClosed High Voltage components in the upper enclosure without verifying the HV DC input bus bars are de-energized.
    • Disconnecting power at the maintenance switch in a Power Link 1000 will not de-energize LVClosed Low Voltage components in that Power Link 1000.

    Pull the maintenance switch to off position

  5. Remove the DC smart cable bus bar safety cover.

  6. Remove the L shaped bus bar safety cover.

  7. Remove the upper bus bar safety cover.

Verify Power Link 1000 is De-Energized

Hold the multimeter's probe tips against the HV DCClosed High Voltage Direct Current input bus bar bolts to verify that voltage is zero.

The illustrated probe contact points on the left side and right side are for the left side and right side HV DCClosed High Voltage Direct Current inputs, respectively. If both HV DCClosed High Voltage Direct Current inputs are present, verify that the power is off on both the HV DCClosed High Voltage Direct Current input's bus bars.

Technical illustration depicts the procedural step.

Disconnect LV Power in Power Link 1000

  1. Remove the following:

    1. Top cap

    2. Front lower and upper covers

  2. Open the upper door.

  3. Verify that HV DC components are de-energized.

  4. Remove HV DC input bus bar safety cover.

    Do not remove safety cover without verifying that HV DC components are de-energized.
  5. Open the upper door.

  6. Locate the 48 V DC breaker in the upper enclosure next to the door hinge.

    Locate the 48 V DC breaker in the upper enclosure next to the door hinge.

  7. Flip down the switch to OFF. The indicator should turn green.

    Flip down the switch to OFF. The indicator should turn green.

  8. Hold the multimeter's probe tips against the output terminal screws to verify that voltage is zero.

    Hold the multimeter's probe tips against the output terminal screws to verify that voltage is zero.